Last Updated | 08/17/2023 02:19 PM |
Project Title | General Contractor for Construction |
Physical Address | View project details and contacts |
City, State (County) | Detroit, MI 48211 (Wayne County) |
Category(s) | Education, Heavy and Highway |
Sub-Category(s) | Elementary School, Middle/Senior High School, Site Development |
Contracting Method | Competitive Bids |
Project Status | Contract Award, Construction start expected October 2023 |
Bids Due | View project details and contacts |
Estimated Value | $3,993,000 [brand] Estimate |
Plans Available from | State Agency |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Oakland International Academy is seeking sealed bids for General Contractor services on a construction project for a 2-story, 17,766 square foot addition to the middle school building located at 8228 Conant Street. 1) Two story sprinkled addition 2) First story: 8,883 sq. ft. 3) Second story: 8,883 sq. ft. 4) Total additional square footage: 17,766 sq. ft. 5) Masonry Construction a. Brick on 8" block b. New brick veneer to match patterning and intent of existing structure c. Rigid insulation between brick air=space and block 6) Limited gypsum board on metal stud construction for some non-classroom function rooms 7) Addition Finishes to match existing finishes, dependent upon owner approval 8) (16) sixteen classrooms, (8) eight per floor 9) (2) two boys and (2) girls bathrooms, (3) three fixtures (sinks & water closets), (1) one per floor 10) (1) one elevator 11) (2) two stair towers 12) (1) teachers Lounge and Teacher's Restroom on second floor 13) Storage, Mechanical and electrical rooms Throughout 14) Mechanical a. (4) Four 12.5 ton units b. (2) Two 4 ton units c. System for addition independent of existing building d. Roof conductors and drains, feed directly to storm e. (2) two water heaters in Mechanical room first floor 15) Electrical a. New electric service to tie into existing service at Main Distribution Panel b. Each floor to have panels for floor c. System for addition independent of existing building 16) Plumbing a. New sanitary lead to tie into existing, contractor to verify exact size, location and flow of direction b. Hi-lo water fountain on each floor c. Service sink on second floor d. Fridge and sink in Teacher's Lounge e. Sprinkler line, domestic line and gas point of entry in Mechanical room (first floor) 17) Fire Alarm a. Per NFPA and Fire Alarm System Manufacturer. 18) Civil a. Site b. Landscape Work is to commence on August 7, 2023. Proposal must include a project timeline with completion by July 1, 2024 and a secured Certificate of Occupancy. |
||||||||||||||||||||||||||||||||||||||||
Details | 2 Stories Above Grade, 17,766 SF.
|
||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |