Similar Projects
Last Updated | 06/23/2023 11:33 AM |
Project Title | Replace North Campground Lift Station |
Physical Address | View project details and contacts |
City, State (County) | Saint Croix Falls, WI 54024 (Polk County) |
Category(s) | Sewer and Water |
Sub-Category(s) | Lift and Pump Stations |
Contracting Method | Competitive Bids |
Project Status | Construction start expected December 2023 , Construction documents |
Bids Due | View project details and contacts |
Estimated Value | $190,000 [brand] Estimate |
Plans Available from | Agency's Affiliate |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | **As of June 23, 2023, bids will rebid. No definite date for the rebid.** SCOPE 8 This section provides information common to two or more technical site work specification sections or 9 items that are of a general nature, and not included in other sections. This section applies to ALL site work, 10 as applicable. Included are the following topics: 11 PART 1 - GENERAL 12 Scope 13 Related Work 14 Referenced Organizations 15 Referenced Documents 16 Quality Assurance 17 Safety 18 Permits 19 Construction Limits 20 Equipment & Materials Furnished by Others 21 Provisions for Future Work 22 Work by Others 23 Submittals 24 Off Site Storage 25 Codes 26 Certificates and Inspections 27 PART 2 - MATERIALS 28 Barricades, Signs, and Warning Devices 29 Temporary Plastic Barrier Fencing 30 PART 3 - EXECUTION 31 Maintenance of Site and Building Access/Egress 32 Continuity of Existing Traffic/Parking and Traffic Control 33 Protection and Continuity of Existing Utilities 34 Protection of Existing Work and Facilities 35 Stormwater/Excavation Water Management SCOPE 9 This section provides information resulting from subsurface investigations completed at the site as part of 10 this project. This section may contain information applicable to ALL sitework, and other technical 11 specification sections, as well. All Contractors are expected to review this information as part of their 12 duties to familiarize themselves with the site. 13 14 Results of the geotechnical investigation apply only to the locations at which data was collected, at the 15 specific time it was collected. Geotechnical conditions may differ elsewhere on the site. 16 17 Prior to making additional investigations of his own using test pits, borings, or other methods; Bidder shall 18 first gain permission from property owner and DFD Project Manager. Geotechnical investigations 19 completed by Bidder shall comply with all applicable requirements of Division 01 through Division 33 of 20 this project |
||||||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |