Last Updated | 08/18/2022 04:01 PM |
Project Title | Monroe Consolidated Drain Improvements |
Physical Address | View project details and contacts |
City, State (County) | Monroe, MI 48161 (Monroe County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Lift and Pump Stations, Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Construction start expected July 2022 |
Bids Due | View project details and contacts |
Estimated Value | $2,342,874 [brand] Estimate |
Plans Available from | County Agency |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Removal of existing pump station and portions of the existing storm sewer system along Lighthouse Road, Venetian Drive, and LaPlaisance Road in Bolles Harbor. Construct a new pump station and install 3,036 feet of storm sewer ranging from 12 inch to 36 inch RCP. Project includes install catch basins and manholes, removing and replacing HMA roadway, culvert bedding, compacted granular backfill, embankment, ditching, utility relocations, and placement of riprap at pump station outfall. Provide slope restoration. Provide traffic control as specified in the special provision for Maintenance of Traffic. Bids will be based on sum total of all bid items using lump sum and unit bid prices. Bid surety in the form of a Bid Bond in an amount equal to 5% of the contract total bid sum, and payable to the Monroe County Drain Commissioner, County Agency will be required of all Bidders. Performance Bond and Lien Bond, equal to the amount of the Contract, will be required of the bidder awarded the Contract. A two-year Maintenance Bond in the amount of 25% of the construction cost will be required from a period beginning upon completion of the Contract work. Bidders must comply with the regulatory and licensing requirements of the State of Michigan. Liquidated damages will be assessed in accordance with Section 108.10 of the Michigan Department of Transportation 2020 Standard Specifications for Construction, except that all references to seasonal limitations will not apply. Liquidated damages will continue to be assessed each calendar day after the contract project completion date until all work on the project is completed, even if those days extend beyond any seasonal limitations. The Bidder agrees that the work will be completed and ready for final payment in accordance with the General Conditions. All work on the project shall be completed by Wednesday, November 1st, 2023. The Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the work on time. No bid may be withdrawn for a period of 120 days after the opening of bids. The Owner reserves the right to reject any or all bids and to waive any informality or irregularity in any bid. |
||||||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||