Similar Projects
Dam Safety Modification Additional Relief Wells and Collector System Upgrades, Mohawk Dam, Warsaw, Ohio
Design
Warsaw, OH 43844

Water Treatment Plant
New Construction
Bidding
$2,750,000 est. value
Mount Eaton, OH

Dpu/Iqa/Project Dry Basement
Bidding
Columbus, OH

DPU/Dist Main - Replacement Parts for HVP2000 Hydraulic Pump
Post-Bid
Columbus, OH

Refurbish Influent Pump No. 2
Post-Bid
Hamilton, OH 45011

Cleaning and Redevelopment of Wells 2 and 4
Results
Xenia, OH 45385

Three (3) Progressive Cavity Sludge Pumps
Results
Springfield, OH 45502

Major Pump Rebuild Project
Bidding
Toledo, OH 43611

Pump Motor Replacement
Post-Bid
New Boston, OH 45662

Supply and Installation of a 12,000 Gallon Horizontal, Doublewall Tank
Results
Circleville, OH 43113

Submersible Vertical Well Pump
Post-Bid
Dayton, OH

DOSD-SWWTP - Weil sump pump
Results
Columbus, OH

Panel Assemblies for KI Miami North Wells
Post-Bid
Dayton, OH

2019 Well Redevelopment Project
Results
Less than $318,827 est. value
Lebanon, OH 45036

Drilling (4) Monitoring Wells, Ohio, USA
Post-Bid
$25,000 to $100,000 est. value
Columbus, OH

Reported 02/15/2020 12:00 AM
Project Title

Additional Relief Wells and Collector System Upgrade

Physical Address View project details and contacts
City, State (County) Warsaw, OH   (Coshocton County)
Category(s) Sewer and Water
Sub-Category(s) Pumps and Wells
Contracting Method Competitive Bids.
Project Status Accepting Letters of Interest
Bids Due View project details and contacts
Estimated Value
Plans Available from Federal Agency
Owner View project details and contacts
Architect View project details and contacts
Description

Project is at Mohawk Dam, located in Jefferson Township, Coshocton County, Ohio northwest of the Village of Nellie. - Installation of 10 new relief wells with individualized housing, conveyance piping (~500 feet total), and outfall structures. The proposed wells will consist of 12-inch diameter stainless steel wire-wrapped screens with filter pack with depths ranging from 102 to 120 feet into glacial outwash (granular soils). Pilot holes were previously completed for screen and filter design. - Installation of new seepage collection system components including 7 manholes (60 to 84-inch precast concrete), ~1,000 feet of piping (24 to 48-inch HDPE), connections, and 3 outfall structures (36 to 48-inch headwalls). - Modification to, and demolition of, select portions of the existing seepage collection system including manholes, piping, and connections. - Earthwork and stone slope protection construction related to the aforementioned demolition, modification, and installation work. Excavated soils will be reused as fill/backfill with excess or unsatisfactory soils disposed in an onsite disposal area.

Details

Division 02 - Existing Conditions, Subsurface Investigation.
Division 03 - Concrete, Cast-in-Place Concrete.
Division 22 - Plumbing, Plumbing Piping, Plumbing Equipment.
Division 26 - Electrical, Instrumentation and Control for Electrical Systems.
Division 33 - Utilities, Water Utilities, Water Utility Distribution Piping, Water Utility Distribution Equipment, Water Utility Pumping Stations, Wells.
Division 44 - Pollution and Waste Control Equipment, Water Pollution Control Equipment.

Bidder's List View project details and contacts
Prospective Bidders View project details and contacts
Project Documents
 Engineered Spec Sheet
 Architectural Plans
 Other Documents