Last Updated | 12/02/2022 11:02 AM |
Project Title | University of Missouri Power Plant - Replace Three Motorized Vehicle Drive Gates |
Physical Address | View project details and contacts |
City, State (County) | Columbia, MO 65211 (Boone County) |
Category(s) | Education, Heavy and Highway, Industrial/Manufacturing |
Sub-Category(s) | College/University, Power Plant, Site Development |
Contracting Method | Competitive Bids |
Project Status | Contract Award, Construction start expected December 2022 |
Bids Due | View project details and contacts |
Estimated Value | $148,466 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Project consists of removed of existing and the install of new cantilever access gates and operators. Work shall be performed under this Contract on campus of the University of Missouri - Columbia at Power Plant. Construction Estimate: $382,000-$425,000. Each bid shall be accompanied by a bid bond, certified check, or cashier's check, acceptable to and payable without condition to The Curators of the University of Missouri, in an amount at least equal to five percent (5%) of bidder's bid including additive alternates. Each Bidder shall complete bid form by manually signing on the proper signature line above and supplying required information called for in connection with the signature. Information is necessary for proper preparation of the Contract, Performance Bond and Payment Bond. Each Bidder shall supply information called for in accompanying "Bidder's Statement of Qualifications. Questions regarding the scope of work should be directed to Greg Linneman with Crockett Engineering Consultants at (573) 447-0292 or glinneman@crockettengineering.com. Questions regarding commercial conditions should be directed to Scott Smith at (573) 882-9217 or smithws@missouri.edu. Information regarding bid results will be available the day following the bid opening by calling (573) 882-1133 A Diversity Participation goal of 10% Combined MBE, WBE, DBE, Veteran Owned Business and 3% SDVE has been established for this contract. The Owner reserves the right to waive informalities in bids and to reject any and all bids. *The value for this project is based on a financial range. The value is listed as the highest possible cost from the range provided by a stakeholder or official project document. |
||||||||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |