Similar Projects
Last Updated | 11/21/2022 10:39 AM |
Project Title | Construction of Wastewater Collection System Addition |
Physical Address | View project details and contacts |
City, State (County) | Guntown, MS 38849 (Lee County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Bidding, Construction start expected December 2022 |
Bids Due | View project details and contacts |
Estimated Value | $877,167 [brand] Estimate |
Plans Available from | Copy Center |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Base Bid Base Bid consists of the following items and approximate quantities: 8" SDR 35 PVC Gravity Sewer Line 2,771 LinFt 8" CL 350 DIP Gravity Sewer Line, PE Encased 670 LinFt 8" CL 350 DIP Restrained-Joint Gravity Sewer Line, PE Encased 106 LinFt 48" Manholes, 0-6' Depth (Vented and Sealed) 16 Each 48" Manhole Extra Depth 32 LinFt 8" Manhole Drop Connection 1 Each 8" GSL Connection to Existing Manhole 2 Each 14" or 16" x 0.250" Bored and Open-Cut Steel Encasement 126 LinFt 8" x 0.188" Open-Cut Steel Encasement 50 LinFt 8"x4" PVC Wye or Tee Branches 10 Each 4" or 6" PVC Service Lines 2,249 LinFt 4" or 6" PVC Cleanouts 13 Each 4" or 6" PVC Two-Way Cleanouts 8 Each Service Connection to Customers 13 Each 8" SDR 35 PVC GSL Stub-Out, All Depths 10 Each CDBG Project Sign and Bulletin Board 1 LS Additional miscellaneous appur- tenant items, including but not limited to, crushed stone founda- tion stabilization, select borrow material, stone riprap, pipeline identification markers, resurfacing, and erosion control items will be a part of the Base Bid. Deductive Alternate Bid #1 (Line "A" Segment 4) Deductive Alternate Bid #1 includes deducting Line "A" Segment 4 as shown on the drawings from the Base Bid. Deductive Alternate Bid #2 (Line "C" Segment 2) Deductive Alternate Bid #2 includes deducting Line "C" Segment 2 as shown on the drawings from the Base Bid. Deductive Alternate Bid #3 (Line "C" Segment 1) Deductive Alternate Bid #3 includes deducting Line "C" Segment 1 as shown on the drawings from the Base Bid. A certified check or bank draft, payable to the order of the "CITY OF GUNTOWN" negotiable U.S. Government bonds (at par value), or a satisfactory Bid Bond executed by the Bidder and an accepted Surety, in an amount equal to five percent (5%) of the total of the Bid shall be submitted with each bid. The successful bidder will be required to furnish a Payment Bond and Performance Bond each in the amount of 100 percent of the contract amount. This project is financed by a Community Development Block Grant and is subject to the rules and regulations thereof. The successful bidder must comply with Section 3 of the Hous- ing and Urban Development Act of 1968 (12 U.S.C. 1701u). CDBG regulations governing the grant re- quire that, to the greatest extent feasible opportunities for contract- ing, subcontracting, training and employment arising in connection with this CDBG project will be extended to Section 3 businesses and Section 3 residents. Minority and Woman Owned Business Enterprises are solicited to bid on this contract as prime contractors and are encouraged to make inquiries regarding potential subcontracting opportunities, equipment, material and/or supply needs. The CITY OF GUNTOWN is an Equal Opportunity Employer, and hereby notifies all Bidders will be afforded the full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, religion, sex, national origin, age, disability, sexual pref- erence, marital or veteran status, or any other legally protected sta- tus in consideration for an award. The successful bidder must comply with the Davis-Bacon Act which requires that all laborers and mechanics shall be paid at rates not less than those determined by the Department of Labor to be prevailing for the locality in which the project is located. The Owner reserves the right to reject any or all bids or to waive any informality in the best interest of the Owner. Bids may be held by the Owner for a period not to exceed 60 days from the date of the opening of Bids for the purpose of reviewing the bids and investigating the qualifications of Bidders, prior to awarding of the Contract. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |