Last Updated | 03/21/2023 10:44 AM |
Project Title | Wastewater Pump Stations Rehabilitation Project |
Physical Address | View project details and contacts |
City, State (County) | Southington, CT 06489 (Hartford County) |
Category(s) | Sewer and Water |
Sub-Category(s) | Lift and Pump Stations |
Contracting Method | Competitive Bids |
Project Status | Construction start expected July 2022 |
Bids Due | View project details and contacts |
Estimated Value | $3,494,950 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Plans for the rehabilitation of 3 pump stations, properties located at 1095 Old Turnpike Road (SPR #1833); 2117 Meriden-Waterbury Road (SPR #1834) and 640 Laning Street (SPR #1835) *Project information, including timeline and contacts, has been obtained through public sources. The content management team continues to pursue additional details; however, the contact(s) listed have yet to disclose or confirm any information. Inquiries should be directed to the contact(s) listed. Old Turnpike, Patton Brood, and Judd Brook Pump Stations - Town of Southington Old Turnpike Pump Station: Replacement of the existing pumps and motors with dry pit submersible style pumps, replacement of the associated equipment, piping, and valves within the dry well, replacement of pump level control equipment and instrumentation, and electrical upgrades for the new pumps and motors, and control panel including two VFDs, as well as a new generator. The work also includes adding piping and valves for a new pump station bypass connection. Repairs and modifications to the building and structures to provide resiliency to the 100 year flood +3ft elevation, including but not limited to demolishing and replacement of the door and louvers. Patton Brook Pump Station: Replacement of the existing pumps and motors with dry pit submersible style pumps, replacement of the associated equipment, piping, and valves within the dry well, replacement of pump level control equipment and instrumentation, and electrical upgrades for the new pumps and motors, and control panel including two VFDs, as well as a new generator. The work also includes adding piping and valves for a new pump station bypass connection. Repairs and modifications to the building and structures to provide resiliency to the 100 year flood +3ft elevation, including but not limited to demolishing and replacement of the door, wet well section, access hatches and louvers. Judd Brook Pump Station: Replacement of the existing pumps and motors with dry pit submersible style pumps, replacement of the associated equipment, piping, and valves within the dry well, replacement of pump level control equipment and instrumentation, and electrical upgrades for the new pumps and motors, and control panel including two VFDs, as well as a new generator. The work also includes adding piping and valves for a new pump station bypass connection. Repairs and modifications to the building and structures to provide resiliency to the 100 year flood +3ft elevation, including but not limited to demolishing and replacement of the door, wet well section, access hatches and louvers |
||||||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |