Reported | 06/08/2022 12:00 AM |
Project Title | KC Bridge Repair |
Physical Address | View project details and contacts |
City, State (County) | LA (Ascension County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Bridge |
Contracting Method | Competitive Bids. |
Project Status | Bidding, Construction Start Expected July 2022 |
Bids Due | View project details and contacts |
Estimated Value | $400,000 [brand] Estimate |
Plans Available from | County Agency |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | This project is trepair spalled concrete in the concrete caps and concrete curbs on the east side of the bridge. On the west side of the bridge, spalled or broken concrete curb and parapet tbe chipped tsound concrete, steel rebar preserved and replaced as needed and concrete and epoxy installed trestore the guardrail supports. The grout and epoxy tbe used will be from the DOTD Qualified Products List (QPL) for this type of work. All bidders should refer tthe "amended scope of repair" document for full details. Project Details: New guard rail and new metal posts are tbe installed (replaced in kind) on west side only. Existing bolts are tbe restored in the repair areas as needed tsecure the existing metal posts (for Guardrail) tthe curb. This project is alstremove rotted sections of the timber piles listed below and splice new pilings in accordance with DOTD Timber Bridge specifications. The project alsincludes the installation of treated timber pilings and boards needed tsecure standalone wingwalls on all four corners of the bridge. This will include 2-12" diameter treated piles and treated 3" oak boards as needed tsecure the embankment. The wingwall lengths will be between seven and ten feet. Furnish/ installing geotextile fabric and three-inch-thick treated oak boards in the mud walls of both end abutments. Bent: South Abutment- Pilings tbe spliced: #2, #3, and #5 Bent: Middle Abutment- Pilings tbe spliced: #3 and #5 Bent: North Abutment- Pilings tbe spliced: #2 and #5 |
||||||||||||||||||||
Details | Bridge, Renovation.
|
||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||
Project Documents |
![]() Engineered Spec Sheet ![]() Architectural Plans ![]() Other Documents |