Last Updated | 05/25/2022 11:24 AM |
Project Title | Water Distribution Storage Tank - Phase 1 at Ray Brook WD |
Physical Address | View project details and contacts |
City, State (County) | North Elba, NY (Essex County) |
Category(s) | Sewer and Water |
Sub-Category(s) | Storage/Water Tanks |
Contracting Method | Competitive Bids. |
Project Status | Results |
Bids Due | View project details and contacts |
Estimated Value | |
Plans Available from | Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | 1. Clear and grub the Project Site. 2. Install temporary distribution storage tank as specified. 3. After the temporary distribution storage tank is placed in operation, remove the existing tanks and piping. 4. Perform all required site work such as grading, retaining walls, preparation of subgrade for the new tank. 5. Construct the new storage tank. 6. After the new storage tank is approved for service, remove temporary storage tank and complete all remaining site improvement items which generally include: * Grading. * Installation of hydrants. * Installation of boulder walls. * Installation of concrete pavement and steps. * Installation of asphalt concrete pavement. * Installation of fencing. * Landscaping work. * Restoration of all areas impacted by the work for this project. |
||||||||||||||
Details |
|
||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |