Last Updated | 09/09/2022 03:04 PM |
Project Title | Lloyd SSRMP - Manhole Rehabilitation - Phase I |
Physical Address | View project details and contacts |
City, State (County) | Evansville, IN 47708 (Vanderburgh County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Contract Award, Construction start expected October 2022 |
Bids Due | View project details and contacts |
Estimated Value | $1,033,375 [brand] Estimate |
Plans Available from | Agency's Affiliate |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | **As of September 9, 2022, project was awarded toCuly Contracting, LLC awarded amount is $1,033,375.20 ** The above-referenced project description includes items that are part of the rehabilitation of two-hundred and twenty-nine (229) manholes in the E-9 Sanitary Sewer Basin, including the lining of approximately one-thousand five-hundred and seventy-four (1,574) vertical feet (VFT) of sanitary sewer manholes, the replacement of approximately two-hundred and two (202) manhole frames and covers, three (3) chimney/riser sections, eight (8) cone sections, nine (9) internal drops, sixty-eight (68) construct benchwalls/rework channels, associated bypass pumping, and an undistributed quantity of adjustment rings for potential frame/cover grade adjustments. The project shall include all necessary work associated with the lining of sanitary sewer manholes, including but not limited to all materials, labor, equipment, traffic control, bypass pumping and/or diversion of sewage flows, cleaning equipment, product installation, and quality control." Work shall also include all supervision, equipment, traffic control, granular backfill, pavement restoration (milling included), flushing, disinfecting, testing and all appurtenances necessary to complete the work shown in the Drawings and Specifications. All work must be ready for satisfactory and continuous operation, in accordance with the Drawings and Specifications. The Evansville Water and Sewer Utility further reserves the right to waive informalities, and to award the contract to the lowest and most responsible bidder (or bidders), all to the advantage of the Evansville Water and Sewer Utility, or to reject all Proposals The rehabilitation of two-hundred and twenty-nine (229) manholes in the E-9 Sanitary Sewer Basin, including the lining of approximately one-thousand five-hundred and seventy-four (1,574) vertical feet (VFT) of sanitary sewer manholes, the replacement of approximately twohundred and two (202) manhole frames and covers, three (3) chimney/riser sections, eight (8) cone sections, nine (9) internal drops, sixty-eight (68) construct benchwalls/rework channels, associated bypass pumping, and an undistributed quantity of adjustment rings for potential frame/cover grade adjustments. The project shall include all necessary work associated with the lining of sanitary sewer manholes, including but not limited to all materials, labor, equipment, traffic control, bypass pumping and/or diversion of sewage flows, cleaning equipment, product installation, and quality control. All work must be ready for satisfactory and continuous operation, in accordance with the Drawings and Specifications |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |