Similar Projects
Last Updated | 04/22/2020 12:11 PM |
Project Title | Grants Creek WWTT Improvements Project |
Physical Address | View project details and contacts |
City, State (County) | Salisbury, NC (Rowan County) |
Category(s) | Sewer and Water |
Sub-Category(s) | Sewage Treatment Plant |
Contracting Method | Competitive Bids. |
Project Status | Results |
Bids Due | View project details and contacts |
Estimated Value | |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | 1. A new 24 MGD influent screening structure with two mechanical multi-rake bar screens and two washer compactors. 2. A new 24 MGD influent pump station with four variable speed wet pit submersible pumps. 3. A new 24 MGD grit removal facility with two mechanically-induced vortex grit units, a bypass channel, two flooded suction grit pumps and two grit classifiers, construction of a flow equalization facility within the existing trickling filters. 4. A new RAS/WAS pump station with three variable speed wet pit submersible RAS pumps and two variable speed wet pit submersible WAS pumps. 5. A new precast electrical building with associated power entrance and metering from the utility provider and a new generator. 6. A new potable water booster pump station that will be required to deliver the required flushing and wash water to the new facilities. 7. A new side stream pump station. 8. Demolition of the remaining internal structures and slab of the existing trickling filters. 9. A new 36-inch influent sewer from the existing influent splitter box to the influent structure. 10. A new equalization and RAS junction box. 11. A new aeration basin influent splitter box. 12. A new 30-inch parallel aeration basin influent. 13. A new aeration basin effluent box. 14. A new 36-inch influent to Secondary Clarifier No. 4. 15. Modifications to the existing chlorine contact chambers. 16. Yard piping, valves and appurtenances to support the new facilities. 17. Installation, maintenance and removal of all erosion and sediment control, and other environmental protection measures, including all permits and approvals required. 18. Testing, start-up, training and miscellaneous work as shown on the Drawings and as specified herein. 19. Site cleanup and restoration. |
||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||
Project Documents |
![]() Engineered Spec Sheet ![]() Architectural Plans ![]() Other Documents |