Last Updated | 10/12/2022 12:06 AM |
Project Title | Reconstruct the Intersection of Madison Street, South Street, and Lake Avenue |
Physical Address | View project details and contacts |
City, State (County) | Woodstock, IL 60098 (McHenry County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Maintenance, Paving/Reconstruction, Site Development |
Contracting Method | Bids by Invitation, Competitive Bids |
Project Status | Construction Commenced, Request for Qualifications, Construction start expected February 2022 |
Bids Due | View project details and contacts |
Estimated Value | $27,554,453 [brand] Estimate |
Plans Available from | State Agency |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | As of May 25, 2022, a general contractor was awarded and construction is underway. *The closed solicitation has been included below for reference: Reconstruct the intersection of Madison Street, South Street, and Lake Avenue into a roundabout in the City of Woodstock. Region 1 District 1 Federal Project # JQHB(492) County(s) McHenry Key Route(s) FAU 39 Marked Route(s) Madison Street Section(s) 16-00114-00-PV (WOODSTOCK) State Job #(s) C-91-314-16 PPS #(s) 1-22030-0000 VBP % 0.00 Completion Date: 135 Working Days Questions not accepted as of January 11, 2022 04:30 PM. Questions directed to: IDOT Contracts Office Harry R. Hanley Building Room 326 2300 South Dirksen Parkway Springfield, IL 62764 (217) 782-7806 Fax: (217) 785-1141 TDD: (217) 524-4875 DOT.DE-Contracts@illinois.gov Unless otherwise indicated, a proposal guaranty is required by bid bonds, cashiers check or properly certified check for not less than 5 (five) percent of the bid amount. If the proposal is accepted and the bidder is declared not responsive, it is hereby agreed that the amount of the proposal guaranty will become the property of the State of Illinois and shall be considered as payment of damages due to the delay and other causes suffered by the State because of the failure to adhere to the procedures required. Otherwise, the bid bond will become void or the proposal guaranty check will be returned to the bidder. Contractors who desire to become prequalified or to renew their prequalification for this letting must file with the Department of Transportation, Bureau of Construction, Room 322, 2300 South Dirksen Parkway, Springfield, Illinois 62764, a Contractors Statement of Experience and Financial Condition no later than 4:30 PM prevailing local time, December 31, 2021. A contractor will not be prequalified for this letting unless the statement is received before the time and day established. The Department reserves the right to reject any and all bids, to waive minor or immaterial irregularities, informalities or technicalities, to advertise for new bids, or to request confirmation or clarification from any bidder regarding a bid. ILDOT - 148 - Reconstruct the Intersection of Madison Street, South Street, and Lake Avenue The work consists of removal of the existing pavement, curb and gutter, and sidewalks and the construction of a roundabout including excavation, topsoil, sodding, Portland cement concrete pavement, HMA pavement, sidewalk, detectable warnings, storm sewer, storm sewer structures, curb and gutter, signs and posts, thermoplastic pavement markings, underground conduits, cables, lighting controller, installation of street lights and other appurtenant construction necessary to complete the project as shown on the plans and described herein. |
||||||||
Details |
|
||||||||
Bidder's List | View project details and contacts | ||||||||
Prospective Bidders | View project details and contacts | ||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |