Project Title | Bridge Replacement BR No S-13-005 Longley Road over the Mulpus Brook |
Physical Address | View project details and contacts |
City, State (County) | Shirley, MA (Middlesex County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Bridge |
Contracting Method | Competitive Bids. |
Project Status | Results |
Bids Due | View project details and contacts |
Estimated Value | $1,490,444 |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | "1.000","Ls","Schedule Of Operations - Fixed Price $7500","100." "0.300","a","Clearing And Grubbing","101." "50.000","Ft","Tree Trimming","102.1" "670.000","Ft","Tree And Plant Protection Fence","102.521" "1.000","Ls","Demolition Of Bridge No. s-13-005","115.1" "1980.000","Cy","Earth Excavation","120." "7.000","Cy","Reinforced Concrete Excavation","127.1" "460.000","Cy","Bridge Excavation","140." "10.000","Cy","Test Pit For Exploration","141.1" "5.000","Cy","Class b Trench Excavation","142." "3.000","Cy","Ordinary Borrow","150." "28.000","Cy","Gravel Borrow","151." "80.000","Cy","Gravel Borrow - Type c","151.01" "220.000","Cy","Gravel Borrow For Bridge Foundation","151.1" "25.000","Ton","Crushed Stone For Integral Abutments","156.13" "328.000","Ton","Crushed Stone For Slope Treatment","156.2" "170.000","Sy","Fine Grading And Compacting - Subgrade Area","170." "1.000","Ls","Inspection And Testing For Asbestos","182.1" "190.000","Ft","Removal Of Asbestos","182.2" "110.000","Ft","Detectable Tape For Water Main Installation","302.081" "165.000","Ft","8 Inch Ductile Iron Water Pipe (Mechanical Joint)","303.08" "180.000","Lb","Ductile Iron Fittings For Water Pipe","309." "190.000","Ft","8 Inch Temporary Service Pipe","345.08" "2.000","Ea","8 x 8 Inch Tapping Sleeve, Valve And Box","369.08" "74.000","Ft","8 Inch Water Pipe Insulation","373.08" "19.000","Cy","Dense Graded Crushed Stone For Sub-Base","402." "360.000","Sy","Pavement Standard Milling","415.1" "810.000","Lb","Calcium Chloride For Roadway Dust Control","440." "1.000","Mgl","Water For Roadway Dust Control","443." "52.000","Ton","Superpave Surface Course - 12.5 Polymer (Ssc - 12.5 - p)","450.231" "22.000","Ton","Superpave Intermediate Course - 19.0 (Sic - 19.0)","450.32" "38.000","Ton","Superpave Base Course - 37.5 (Sbc - 37.5)","450.42" "17.000","Ton","Superpave Bridge Surface Course - 12.5 Polymer (Ssc-b - 12.5 - p)","450.611" "17.000","Ton","Superpave Bridge Protective Course – 12.5 (Spc-b - 12.5)","450.71" "69.000","Gal","Asphalt Emulsion For Tack Coat","452." "400.000","Ft","Hma Joint Sealant","453." "2.000","Ton","Temporary Asphalt Patching","472." "100.000","Ft","Granite Curb Type Va5 - Straight","505." "228.000","Ft","Hot Mix Asphalt Curb Type 3","570.3" "150.000","Ft","Guardrail, Tl-2 (Single Faced)","620.12" "25.000","Ft","Guardrail - Curved, Tl-2 (Single Faced)","620.32" "3.000","Ea","Trailing Anchorage","627.1" "1.000","Ea","Transition To Nchrp 350 Guardrail","628.21" "4.000","Ea","Transition To Bridge Rail","628.24" "450.000","Ft","Highway Guard Removed And Discarded","630.2" "100.000","Ft","Temporary Fence","657." "200.000","Ft","Temporary Fence For Site Screening","657.1" "2.000","Ea","Silt Sack","697.1" "450.000","Ft","Floating Silt Fence","697.2" "660.000","Sy","Geotextile Fabric For Permanent Erosion Control","698.4" "10.000","Mo","Engineers Field Office And Equipment (Type a)","740." "1.000","Ls","Mobilization","748." "60.000","Cy","Loam Borrow","751." "8.000","Lb","Seed For Erosion Control","765.2" "400.000","Sy","Seeding - Low Upland Mix","765.411" "100.000","Sy","Wetland Mix - Part Shade","765.555" "530.000","Ft","Sediment Control Barrier","767.121" "370.000","Sy","Straw Mulch","767.31" "370.000","Sy","Jute Mesh Erosion Control Fabric","767.731" "310.000","Ft","Pavement Milling Mulch Under Guard Rail","769." "15.000","Sf","Warning-Regulatory And Route Marker - Aluminum Panel (Type a)","832." "5.000","Ea","Demountable Reflectorized Delineator - Guard Rail","833.5" "7.000","Ea","Delineation For Guard Rail Termini","833.7" "2.000","Ea","Sign Sup (n/Guide)+Rte Mkr w/1 Brkway Post Assembly - Steel","847.1" "225.000","Sf","Safety Signing For Traffic Management","852." "6.000","Ea","Portable Breakaway Barricade Type Iii","853.1" "40.000","Ft","Temporary Barrier (Tl-2)","853.2" "40.000","Ft","Temporary Barrier Removed And Reset","853.21" "300.000","Day","Reflectorized Drum","859." "2.000","Ea","Traffic Sign Removed And Stacked","874.4" "14.000","Cy","3000 Psi, 1.5 Inch, 470 Cement Concrete","903." "460.000","Ft","Steel Pile Hp 10 x 57","942.102" "2.000","Ea","Dynamic Load Test By Contractor","948.41" "12.000","Ea","Pile Shoes","948.5" "1160.000","Ton","Dumped Riprap","983." "220.000","Cy","Streambed Armor","983.522" "1.000","Ea","Temporary Utility Bridge","992.321" "1.000","Ls","Bridge Structure, Bridge No. s-13-005","995.01" |
||||||||||||||||||||
Details |
|
||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||
Project Documents |
![]() Engineered Spec Sheet ![]() Architectural Plans ![]() Other Documents |