Reported | 11/27/2021 12:00 AM |
Project Title | MILCON ERCIP Microgrid |
Physical Address | View project details and contacts |
City, State (County) | Mountain View, CA (Santa Clara County) |
Category(s) | Industrial/Manufacturing |
Sub-Category(s) | Electric Substation |
Contracting Method | Competitive Bids. |
Project Status | Accepting Letters of Interest |
Bids Due | View project details and contacts |
Estimated Value | $5,000,000 to $15,000,000 |
Plans Available from | Federal Agency |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Contractor shall install a microgrid system that will have full islanding capability. The microgrid system will incorporate a roof-mounted 750kW photovoltaic (PV) solar system; a 750kWh battery energy storage system (BESS); an 800kW diesel backup generation system, with a 10,000 gallon fuel storage tank; switchgear building. The photovoltaic system will be installed on the roofs of the headquarters building. Period of performance is estimated to be 280 calendar days from notice to proceed. |
||||||||||||
Details | Electric Substation, New Construction.
|
||||||||||||
Bidder's List | View project details and contacts | ||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |