Similar Projects
Last Updated | 02/26/2021 04:16 PM |
Project Title | Digester Upgrade and Rehabilitation Phase 1 |
Physical Address | View project details and contacts |
City, State (County) | Roanoke, VA (Roanoke City County) |
Category(s) | Sewer and Water |
Sub-Category(s) | Water Treatment Plant |
Contracting Method | Competitive Bids. |
Project Status | Results |
Bids Due | View project details and contacts |
Estimated Value | |
Plans Available from | Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | The Digester Upgrade and Rehabilitation Phase 1 Project consist of upgrades to the primary digesters including demolition and replacement of three concrete covers, miscellaneous concrete repairs, new mixing systems, new instrumentation, piping and valving modification and improvements to the digester control system. Improvements to one secondary digester include the removal and replacement of the existing membrane cover system. The Contractor is responsible for all digester draining and cleaning costs required to perform the proposed work. Minor thickening improvements include new sludge piping and valving in the dissolved air flotation building and new sludge yard piping to the adjacent blend tank. The Project also includes construction of related electrical, control and information system components for digester operations, and all piping, valves, grading, paving, erosion and sediment control and associated work necessary to render the facilities complete and operational. |
||||||||||||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |