Last Updated | 09/28/2022 01:54 AM |
Project Title | State Street and Dora Street Rehabilitation Project |
Physical Address | View project details and contacts |
City, State (County) | Ukiah, CA 95482 (Mendocino County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Maintenance, Paving/Reconstruction, Site Development |
Contracting Method | Competitive Bids |
Project Status | Contract Award, Construction start expected September 2022 |
Bids Due | View project details and contacts |
Estimated Value | $1,511,530 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | All of the work to be performed is within the City of Ukiah. On South Dora Street from Beacon Lane to Wabash Avenue: work involves complete full width surface grinding down 2" and placing 2: AC overlay over existing asphalt concrete pavement. On South Dora Street from Wabash Avenue to Washington Avenue: work involves complete reconstruction of roadway including full excavation and placing 6" AC over 12" class II base with soil stabilization fabric. ADA curb ramps will be installed at locations shown and listed in the specifications. On South State Street from Beacon Lane to Cherry Street: work involves edge grinding down 2" and placing 2" AC overlay over existing asphalt concrete pavement. ADA curb ramps will be installed at location shown and listed in the specifications. Bid Bond Percentage: 10% Liquidated Damages: $500.00 Per Calendar Day Project Duration: 50 Work Days |
||||
Details |
|
||||
Bidder's List | View project details and contacts | ||||
Prospective Bidders | View project details and contacts | ||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |