Similar Projects
Malin Road Culvert Replacement
Infrastructure
Bidding
Newtown Square, PA 19073

Kish Park Pond Improvements
Infrastructure
Bidding
Lewistown, PA 17044

Levee Rehabilitation Project
Post-Bid
PA

Mattes Road Culvert Replacement
Post-Bid
Friendsville, PA 18818

Mchenry Road Culvert Project
Results
Benton, PA 17814

Upper Julian Pike and Rose Drive Culvert Replacements Project
Results
$55,000 to $75,000 est. value
Patton, PA 16803

Shoulder and Slope Rehabilitation
Infrastructure
Bidding
PA

Roberts Road Culvert Replacement Project
Post-Bid
Littlestown, PA 17340

Storm Sewer Culvert Replacements
Results
Dover, PA 17315

Loading Dock Drain System Replacement
Infrastructure
Bidding
Pittsburgh, PA

Streambank Restoration on Crouse Run Along Sample Road, From the Confluence with Pine Creek to Just Downstream of Royalview Drive
Post-Bid
Allison Park, PA 15101

Precast Concrete Basins, Risers, Grates and Frames
Results
PA

23 WHM SGL 95 Eiler Road Project
Infrastructure
Bidding
West Sunbury, PA 16061

Mountain Road Culvert Project
Post-Bid
Less than $105,000 est. value
Benton, PA 17814

Danville - Mahoning Creek Flood Protection Project
Results
$1,000,000 to $2,000,000 est. value
Danville, PA 17821

Last Updated 03/24/2022 03:02 PM
Project Title

Secant Wall Construction, Montgomery L/D, Ohio River, PA

Physical Address View project details and contacts
City, State (County) Monaca, PA   (Beaver County)
Category(s) Heavy and Highway
Sub-Category(s) Shoreline/Erosion/Drainage
Contracting Method Competitive Bids.
Project Status Results
Bids Due View project details and contacts
Estimated Value $5,000,000 to $10,000,000
Plans Available from
Owner View project details and contacts
Architect View project details and contacts
Description

The U.S. Army Corps of Engineers, Pittsburgh District, has a requirement for construction of a secant pile wall at Montgomery Locks and Dam, Ohio River, PA. The secant pile wall will be constructed downstream of Gate Bay 1, through the concrete apron. The major features of the contract are identified below: Installation of a bulkhead system on top of the fixed crest dam, commonly referred to as “flashboards”; Installation of instrumentation and monitoring devices including on top of the apron underwater; Drilling of exploratory test borings at the center of piles shown on the contract drawings; If extensive voids are present, as directed in specifications, grouting under the apron may be required, prior to drilling the Primary/Secondary piles; Construction of demonstration secant piles; Demolition of existing concrete baffles, as required; Layout of secant wall; Removal and disposal of limited portions of concrete apron; Drilling and placement of primary piles; Drilling and placement of secondary piles; Pressure grouting at both ends of secant wall; Under the apron grouting may be required to fill voids created by construction. The work is to be performed downstream of Gate Bay 1, with the centerline of the secant wall 14’ riverward off of the centerline of Pier 1. Water elevations shown below may vary and all elevations shown are for information purposes only. Typical downstream pool elevation at Montgomery Locks and Dam is 664.5’, with the top of apron elevation of 647.5’. Top of alluvium, which is just under the concrete apron, is elevation 642.5’ and the top of rock elevation is elevation 620.0’+/-. Pool elevations will not be adjusted for this contract, though altered Gate Schedules will be followed in order to aid the Contractor with reduced turbulence. Construction of the secant wall will involve drilling through the 5’ thick concrete apron, alluvium, and an estimated 18’ into rock for the secondary piles. Each pile is approximately 4’-0” in diameter, and will be filled with tremie concrete, or a steel wide flange reinforcement beam and tremie concrete. There are 17 piles that are shown on the contract drawings, 10 secondary piles (tremie concrete with steel wide flange reinforcement beam) and 7 Primary Piles (tremie concrete alone). All work will be performed from the Contractor’s floating plant located downstream of Gate Bay 1 and the fixed crest dam. Dive work is to be expected for this project. This project shall be completed, including final submittals, by 31 December 2022. Off-site disposal of concrete, alluvium, and rock will be required. Debris and rubbish shall be disposed of at a properly permitted facility licensed to accept waste or recyclable materials as applicable. Construction work will occur in close proximity to waterway traffic and operating lock and dam gates. The existing lock chambers are currently operated 24 hours a day, 7 days a week.

Details

Division 31 - Earthwork, Erosion and Sedimentation Controls.
Division 33 - Utilities, Storm Drainage Utilities, Ponds and Reservoirs.
Division 35 - Waterway and Marine Construction, Shoreline Protection, Seawalls, Waterway Construction and Equipment.

Bidder's List View project details and contacts
Prospective Bidders View project details and contacts
Project Documents
 Engineered Spec Sheet
 Architectural Plans
 Other Documents