Project Title

New Pumphouse Power Upgrade Installation at Belleayre Ski Center

Physical Address View project details and contacts
City, State (County) Highmount, NY 12441   (Ulster County)
Category(s) Single Trades
Sub-Category(s) Electric
Contracting Method Competitive Bids.
Project Status Results
Bids Due View project details and contacts
Estimated Value
Plans Available from
Owner View project details and contacts
Architect View project details and contacts
Description

Work for Single Prime Contract” for a general description and the Technical Specification Sections for the specific descriptions; but in a general overview of the contract scope includes: Install two (2) 6” conduits from Switchgear 01 to New Upper Pumphouse location - approximately 3200 feet. Pull three (3) 4/0 cables and (1) 2/0 ground through one (1) of the conduits; other conduit shall be terminated at future transformer location and capped for future use. Install two (2) 4 circuit sectionalizers and vaults. Install three (3) vaults for the three (3) 2000KVA transformers. Install the transformers onto the vaults. Connect one sectionalizer to existing 4/0 cables that currently feed existing 2500KVA transformer. Connect existing 2500KVA transformer to sectionalizer and connect one of the new 2000KVA transformers to the other circuit in the sectionalizer. Connect new feed to the second sectionalizer and terminate the other two (2) 2000KVA transformers to the second sectionalizer.

Details

Division 26 - Electrical.

Bidder's List View project details and contacts
Prospective Bidders View project details and contacts
Project Documents
 Engineered Spec Sheet
 Architectural Plans
 Other Documents