Similar Projects
Last Updated | 06/12/2023 08:37 AM |
Project Title | Coal Yard Reclamation - City of Ames |
Physical Address | View project details and contacts |
City, State (County) | Ames, IA 50010 (Story County) |
Category(s) | Heavy and Highway, Industrial/Manufacturing |
Sub-Category(s) | Power Plant, Site Development |
Contracting Method | Competitive Bids |
Project Status | Conceptual Design, Construction start expected March 2026 |
Bids Due | View project details and contacts |
Estimated Value | $450,000 [brand] Estimate |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | In the spring of 2016, the Power Plant was converted from coal-fired to natural gas-fired. This project is to reclaim the area used for coal storage by transforming it into a green space. The project is included in the city's 2023-2027 capital improvement plan (CIP). As of January 3, 2023, further details regarding design and construction have not been identified. *Project information has been obtained through a public capital improvement plan (CIP). A CIP is a financial schedule for short- and long-range projects which is updated regularly. Information listed in the CIP often evolves based on funding availability and the project details, including timeline and value, are subject to change. The content management team will continue to pursue additional details as they become available. As of June 12, 2023, no rebid information available |
||||||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |