Similar Projects
Reported | 06/21/2022 08:36 AM |
Project Title | 300 West Downtown Storm Drain - Phase I - City of Provo |
Physical Address | View project details and contacts |
City, State (County) | Provo, UT 84604 (Utah County) |
Category(s) | Sewer and Water |
Sub-Category(s) | Storm/Sewers |
Contracting Method | Competitive Bids. |
Project Status | Conceptual Design, Construction Start Expected March 2026 |
Bids Due | View project details and contacts |
Estimated Value | Less than $1,750,000 |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | This project will consist of 18" - 42" storm drain pipe along 300 West, from 500 North to 600 South, where it would connect into the existing South Central Storm Drain. The area served would be over 200 acres between Freedom Blvd. and 500 West, from 600 South to approx. 650 North. As of June 17, 2022, this project is currently in the FY 2023-2027 CIP. Funding for this project is allotted in the city's capital improvement plan for construction FY 2025. A firm timeline has not been established; however, construction is scheduled for Fiscal Year 2025. *Project information has been obtained through a public capital improvement plan (CIP). A CIP is a financial schedule for short- and long-range projects which is updated regularly. Information listed in the CIP often evolves based on funding availability and the project details, including timeline and value, are subject to change. The content management team will continue to pursue additional details as they become available. |
||||
Details |
|
||||
Bidder's List | View project details and contacts | ||||
Prospective Bidders | View project details and contacts | ||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |