Similar Projects
Last Updated | 06/24/2023 11:32 AM |
Project Title | Outfall Jetty Rehabilitation Mamaroneck Wastewater Treatment Plant |
Physical Address | View project details and contacts |
City, State (County) | Mamaroneck, NY 10543 (Westchester County) |
Category(s) | Single Trades |
Sub-Category(s) | Plumbing |
Contracting Method | Competitive Bids |
Project Status | Results, Construction start expected August 2023 |
Bids Due | View project details and contacts |
Estimated Value | $6,058,700 [brand] Estimate |
Plans Available from | Agency's Affiliate |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Reference Number 0000316873 The work under this contract consists of providing all necessary labor, material and equipment required to construct a new steel sheet pile bulkhead around the existing effluent Outfall Jetty, located within the Village of Mamaroneck's Harbor Island Park. The new steel sheet pile bulkhead, using marine grade steel, will be constructed to the same finished elevation as the existing steel bulkhead and approximately 2' feet to the waterside of the existing steel bulkhead. Some portions of the new bulkhead will be constructed using stone revetment to the waterside of the existing bulkhead in areas where the new steel sheet piling is not being installed. A new concrete pile cap will be constructed on top of the new steel sheet piling which will also serve as a foundation for a new perimeter fence. In addition, pervious pavement walkways, decorative lighting, benches, fencing, and grass areas will be installed on the surface area of the rehabilitated jetty (Bid range: $6,400,000.00 to $7,000,000.00). Filling the annular space between the new and existing steel sheet pile bulkheads with 3/4 " crushed stone. o Constructing stone revetment waterward of the existing bulkhead in areas where new steel sheet piling is not being installed. o Installing a concrete pile cap on top of the new steel sheet piling which will also serve as a foundation for a new perimeter fence. o Installing pervious pavement walkways, decorative lighting, benches, fencing, grass areas and planting beds on top of the rehabilitated jetty. General Requirements - Bid Deposit Required - Insurance Required - Prevailing Wage Required Contact Information John Coelho 914-995-5144 jjcb@westchestergov.com Completion- 730 consecutive calendar days |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |