Similar Projects
Reported | 06/23/2022 04:52 PM |
Project Title | Canal Replacement Cost Share - Segment 5 - City of Brentwood |
Physical Address | View project details and contacts |
City, State (County) | Brentwood, CA (Contra Costa County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Shoreline/Erosion/Drainage |
Contracting Method | Competitive Bids. |
Project Status | Conceptual Design, Construction Start Expected June 2022 |
Bids Due | View project details and contacts |
Estimated Value | $4,986,270 |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | The City currently utilizes the Contra Costa Water District ("CCWD") conveyance facilities (Contra Costa Canal, pumps, underground pipes and screens) for the delivery of Delta water to the Brentwood Water Treatment Plant. Through an agreement with CCWD, the City will pay for its proportional share of upgrades to CCWD's facilities. This project accounts for the City's proportional share of the projected costs for CCWD's Canal Replacement Project (Segment 5). Project is included in the City of Brentwood's FY 2022/23 - FY 2026/27 CIP. As of June 22, 2022, information regarding a design team or a general contractor is not available. Construction is anticipated from 2022 to 2024.* *Project information has been obtained through a public capital improvement plan (CIP). A CIP is a financial schedule for short- and long-range projects which is updated regularly. Information listed in the CIP often evolves based on funding availability and the project details, including timeline and value, are subject to change. The content management team will continue to pursue additional details as they become available. |
||||||
Details |
|
||||||
Bidder's List | View project details and contacts | ||||||
Prospective Bidders | View project details and contacts | ||||||
Project Documents |
![]() Engineered Spec Sheet ![]() Architectural Plans ![]() Other Documents |