Project Title | Railroad Alley Sewer Separation |
Physical Address | View project details and contacts |
City, State (County) | Glasgow, MT 59230 (Valley County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Maintenance, Paving/Reconstruction, Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Construction start expected September 2022 |
Bids Due | View project details and contacts |
Estimated Value | $600,000 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Stormwater Improvements, Storm Drain and Paving The project generally consists of, but is not necessarily limited to, the following major items: o Installation of new storm drain line in Railroad Alley, including new pipe, bedding, backfill and pre-cast manholes. o Installation of new lateral piping to connect existing storm drain inlets to new storm drain line. o Disconnection of the existing storm drain inlets from the sewer system. o Miscellaneous surface restoration. CONTRACTOR(s) are required to have registered with the DLI prior to bidding on this project. All laborers and mechanics employed by CONTRACTOR(s) or subcontractors in performance of the construction work shall be paid wages at rates as may be required by the laws of the state of Montana in accordance with the schedule of Montana Prevailing Wage Rates established by the Montana Department of Labor and Industry included in the Project Manual. Payment of an additional $25.00 is required for express mail. The CONTRACTOR must ensure that employees and applicants for employment are not discriminated against because of their race, color, religion, sex, or national origin. Each bid or proposal must be accompanied by a Certified Check, Cashier's Check, or Bid Bond payable to City of Glasgow, in an amount not less than ten percent (10%) of the total amount of the bid. Successful BIDDERS shall furnish an approved Construction Performance Bond and a Construction (Labor and Materials) Payment Bond, each in the amount of one hundred percent (100%) of the contract amount. Insurance as required shall be provided by the successful BIDDER(s) and a certificate(s) of that insurance shall be provided. A bid may not be withdrawn after the scheduled time for the public opening of the Bids specified above unless it meets requirements and procedures outlined in Article 16.02 of the Instructions to Bidders. The right is reserved to reject any or all Proposals received, to waive informalities, to postpone the award of the contract for a period of not to exceed sixty (60), and to accept the lowest responsive and responsible bid which is in the best interest of the City of Glasgow. The CONTRACTOR(s) is required to be an Equal Opportunity Employer. |
||||||||||
Details |
|
||||||||||
Bidder's List | View project details and contacts | ||||||||||
Prospective Bidders | View project details and contacts | ||||||||||
Project Documents |