Similar Projects
Last Updated | 01/03/2024 06:02 PM |
Project Title | UNL East Campus Utility Plant Boilers 4&5 Lower Drum Steam Heating Coil & Automated Blowdown System |
Physical Address | View project details and contacts |
City, State (County) | Lincoln, NE 68503 (Lancaster County) |
Category(s) | Single Trades |
Sub-Category(s) | HVAC |
Contracting Method | Competitive Bids |
Project Status | Results, Construction start expected January 2024 |
Bids Due | View project details and contacts |
Estimated Value | $545,049 [brand] Estimate |
Plans Available from | Agency's Affiliate |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | The University of Nebraska is requesting proposals from qualified bidders to provide all material and labor to design, furnish, install and place in successful operation East Campus Utility Plant Boilers 4 & 5 Lower Drum Steam Heating Coil & Automated Blowdown System. Please reference the project documents for additional information. 12/8/2023 6:00 PM (ET) Non-Participation Bidder Questions Deadline 12/12/2023 6:00 PM (ET) Non-Participation Final Addendum Deadline Bid Security is required. Make payable to: Board of Regents of the University of Nebraska, in the amount of 5% of the Lump Sum Base Bid Amount. Bid Security shall be one of: cashier's check, certified check, or Bid Bond issued by a Surety licensed to conduct business in the State of Nebraska. Form of Bid Bond is AIA Document A310. Any agent signing a bid bond on behalf of the Surety must attach a Power of Attorney effectively evidencing the agent's authority to bind the Surety to the performance of the Bid Bond. The selected Bidder will be required to furnish an Owner's Protective Bond as required by Nebraska Revised Statutes 52-118, and as specified in Section 00 72 13 - General Conditions, in the amount equal to 100% of the Contract Sum to cover contractual performance and as security for the payment of all obligations of the Contractor to all laborers and mechanics for labor, and for all materials and equipment used in the completion of the project. REJECTION OF BIDS A. Bidder acknowledges right of Owner to reject any or all bids and to waive any informalities or irregularities which do not materially affect the integrity or effectiveness of the competitive bidding process. B. Bidder recognizes right of Owner to reject a bid if Bidder has failed to: 1. Furnish the required Bid Security. 2. Submit data required by Bidding Documents. 3. Complete in any way the electronic submission or required attachments. 4. Attend the pre-bid meeting where attendance at such meeting is required as a part of the Bidder qualification process. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |