Similar Projects
Access Control Point Program Design Build II -- RFI(2)
Design

Z1DZ--Construction MATOC - above $500K - MS Region (Biloxi 520 and Jackson 586)
Design
$500,000 to $15,000,000 est. value
Eglin AFB, Panama City, Pensacola, FL

Operation and Maintenance of Government-Owned Facilities and Equipment, Jim Woodruff Lock & Dam and Lake Seminole Project, Florida and Georgia
Bidding

Demolition and New Construction of Maintenance Building
New Construction, Demolition - 2,400 SF
Bidding
Niceville, FL

Sources Sought Synopsis for United States Coast Guard (USCG) Disaster Reconstitution Multiple Award Construction Contract
Post-Bid
$3,000,000 to $15,000,000,000 est. value

Eglin AFB & Hurlburt Field Multiple Award Construction Contract
Post-Bid
Less than $450,000,000 est. value
Eglin AFB, FL

Army Mechanical MATOC
Results
Less than $2,000,000 est. value

Building Improvments (Beautification)
Renovation
Results
Hurlburt Field, FL 32544

Indefinite Delivery / Indefinite Quantity (IDIQ) Global Contingency Construction (GCC) Multiple Award Contract (MAC)
Design
Less than $5,000,000,000 est. value

Defense Health Agency - Medical Facility Operations and Maintenance
Bidding
$2,500 to $90,000,000 est. value

D/B Southeast MATOC - Phase 2
Post-Bid
$1,000,000 to $170,000,000 est. value

Air Force Contract Augmentation Program (AFCAP) V
Results

SB Fuels Multiple Award Task Order Contract (MATOC)
Design
Less than $349,000,000 est. value
Washington, DC

Fire Training Facility Repair
Post-Bid
Hurlburt Field, FL 32544

Indefinite Quantity Construction Contract - East Central and Southwest Florida
Results
$2,000,000 est. value

Last Updated 08/26/2020 03:59 PM
Project Title

ACURL Phase 2 Eglin AFB, FL

Physical Address View project details and contacts
City, State (County) Eglin AFB, FL 32542   (Okaloosa County)
Category(s) Government/Public
Sub-Category(s) Misc. Buildings
Contracting Method Design-Build.
Project Status Pre-Solicitation
Bids Due View project details and contacts
Estimated Value $10,000,000 to $25,000,000
Plans Available from
Owner View project details and contacts
Architect View project details and contacts
Description

The project scope of the ACURL Complex will be for the design and construction of a reprogramming facility, a second phase 2-story addition, approximately 34,669 sf and renovations of approximately 1,800 gsf with reinforced concrete foundation and floor slab, steel structure, masonry walls, metal roof, HVAC, fire detection and protection, and mass notification system. This phase 2 facility will include an electronics lab and control room, lab tech support offices, separate smaller electronic work rooms, a NOC (Network Operations Center), office and engineering support areas that will develop mission data (MD), receiving area and classified material storage areas at Secret/Collateral and SAP levels, and a large training room with AV/VTC capabilities. The phase 2 addition will be primarily accessed through the phase 1 entry which will serve as the ACURL complex main entry. The training function will be a separate area from the other phase 2 functions and have a dedicated exterior entry. Department of Defense (DoD) principles for high performance and sustainable building requirements will be included in the design and construction of the project in accordance with federal laws and Executive Orders. Low Impact Development features will be included in the design and construction of this project as appropriate. This project will provide Anti-Terrorism/Force Protection (AT/FP) features and comply with AT/FP regulations and physical security mitigation in accordance with DoD Minimum Anti-Terrorism Standards for Buildings. Appropriate cybersecurity measures will be applied to the facility-related control systems in accordance with current DoD criteria.

Details

1 Misc. Buildings, 2 Stories Above Grade, Approximately 34,669 SF Addition.
Division 03 - Concrete, Concrete Forming and Accessories, Cast-in-Place Concrete.
Division 04 - Masonry, Unit Masonry.
Division 06 - Wood, Plastics, and Composites, Rough Carpentry, Finish Carpentry, Millwork.
Division 07 - Thermal and Moisture Protection, Dampproofing and Waterproofing, Thermal Protection, Weather Barriers.
Division 08 - Openings, Doors and Frames, Entrances, Windows.
Division 09 - Finishes, Plaster and Gypsum Board, Acoustical Ceilings, Flooring, Carpeting, Acoustic Treatment, Painting.
Division 12 - Furnishings.
Division 21 - Fire Suppression, Water-Based Fire-Suppression Systems, Fire-Extinguishing Systems.
Division 22 - Plumbing, Instrumentation and Control for Plumbing, Plumbing Piping, Plumbing Equipment, Plumbing Fixtures, Drinking Fountains and Water Coolers.
Division 23 - Heating, Ventilating, and Air Conditioning (HVAC), Instrumentation and Control for HVAC, HVAC Air Distribution, Central HVAC Equipment.
Division 26 - Electrical, Power Distribution Units, Lighting, Interior Lighting, Emergency Lighting, Exit Signs, Exterior Lighting.
Division 27 - Communications, Structured Cabling, Data Communications, Voice Communications.
Division 28 - Electronic Safety and Security.
Division 31 - Earthwork, Clearing and Grubbing, Grading, Soil Treatment.
Division 32 - Exterior Improvements, Flexible Paving, Asphalt Paving, Rigid Paving, Concrete Paving, Curbs, Gutters, Sidewalks, and Driveways, Paving Specialties, Parking Bumpers, Pavement Markings, Fences and Gates, Irrigation, Planting.
Division 33 - Utilities.

Bidder's List View project details and contacts
Prospective Bidders View project details and contacts
Project Documents
 Engineered Spec Sheet
 Architectural Plans
 Other Documents