Last Updated | 03/01/2023 06:02 PM |
Project Title | Interlake Tunnel Project |
Physical Address | View project details and contacts |
City, State (County) | Bradley, CA 93426 (Monterey County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Dam/Tunnel, Site Development |
Contracting Method | Competitive Bids |
Project Status | Schematic Drawings, Construction start expected June 2028 |
Bids Due | View project details and contacts |
Estimated Value | $60,000,000 [brand] Estimate |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Interlake Tunnel Project. Operationally, the Interlake Tunnel would divert water from Nacimiento Reservoir to San Antonio Reservoir that would have otherwise been spilled at Nacimiento Dam. The Nacimiento River basin produces nearly three times the average annual flow of the San Antonio River basin, therefore, capturing high Nacimiento River flows and diverting those flows to San Antonio Reservoir increases the overall storage capacity of the system. The Interlake Tunnel has been divided into three phases: project feasibility, including preliminary engineering and water rights requirements analysis; pre-construction tasks, including environmental review, permit applications, geotechnical and final design, right-of-way acquisition and financing arrangements; and construction. Per the owner, as of March 1, 2023, the owner states that a design team has been selected but information is not available at this time. The owner states that construction is about 5 years out. |
||||||
Details |
|
||||||
Bidder's List | View project details and contacts | ||||||
Prospective Bidders | View project details and contacts | ||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |