Last Updated | 04/26/2023 05:16 PM |
Project Title | Furnish and Install Shade Shelters at 18 District Sites, Group 3A and Group 3B |
Physical Address | View project details and contacts |
City, State (County) | San Diego, CA 92101 (San Diego County) |
Category(s) | Education, Heavy and Highway |
Sub-Category(s) | Elementary School, Middle/Senior High School, Site Development |
Contracting Method | Bids by Invitation, Competitive Bids |
Project Status | Contract Award, Construction start expected May 2023 |
Bids Due | View project details and contacts |
Estimated Value | $3,170,573 [brand] Estimate |
Plans Available from | Copy Center |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | As of April 4, 2023 , this project has not yet been awarded. The project is expected to be awarded on April 25, 2023. Furnish and Install Shade Shelters at 1 District Sites, Group 3A and Group 3B Other Details See attached advertisement for project-specific requirements and how to obtain bid documents, plans, and specifications. Notes The Board of Education of the San Diego Unified School District of San Diego County, California, invites and will receive electronic-only bids from qualified firms for furnishing all labor, materials, equipment, and supplies for this project. Bids/Proposals submitted after such time will not be accepted. Each bid shall be in accordance with all terms, conditions, plans, specifications, and any other documents that comprise the bid package. The District reserves the right to reject any and all bids and to waive any irregularities or informalities in any bids or in the bidding process. Special Notices Local Programs & Policies See attached advertisement for requirements related to Department of Industrial Relations (DIR), Disabled Veteran Business (DVB) Participation Program, Project Stabilization Agreement (PSA), and District pre-qualification. No bidder may withdraw his bid for a period of 90 days after the date set for the opening of bids. Liquidated Damages Please refer to Supplementary Conditions in Bid Documents for project specific liquidated damages. Estimated Bid Value Range between $5 million to $5.5 million Start/Delivery Date 4/26/2023 Project Duration Substantial Completion by 02/29/2024 *The value for this project is based on a financial range. The value is listed as the highest possible cost from the range provided by a stakeholder or official project document. Mandatory site visits are scheduled for projects in Group 3A and Group 3B at 9:00 a.m. on MONDAY, MARCH 13, 2023, outside the main office of Longfellow Elementary School, 5055 July St, San Diego, CA 92110. Upon completion, all contractors will proceed to Porter Elementary School, 445 South 47th St, San Diego, CA 92113. Upon completion, all contractors will proceed to Webster Elementary School, 4801 Elm St, San Diego, CA 92102. Upon completion, all contractors will proceed to Hancock Elementary School, 3303 Taussig St, San Diego, CA 92124. Upon completion, all contractors will proceed to Miller Elementary School, 4343 Shields St, San Diego, CA 92124. Upon completion all contractors will proceed to Vista Grande Elementary School, 5606 Antigua Blvd, San Diego, CA 92124. |
||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |