Last Updated | 06/29/2023 11:20 AM |
Project Title | 2023 Countywide Surface Treatment |
Physical Address | View project details and contacts |
City, State (County) | Pittsburg, CA 94565 (Contra Costa County) |
Category(s) | Single Trades |
Sub-Category(s) | Concrete |
Contracting Method | Competitive Bids |
Project Status | Contract Award, Construction start expected July 2023 |
Bids Due | View project details and contacts |
Estimated Value | $8,115,837 [brand] Estimate |
Plans Available from | County Agency - 03/21/23 |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | **As of June 29, 2023, project was awarded to Northwest Paving, Inc., awarded amount is $8,115,837.20.** The work to be done generally consists of surface treatment work in the unincorporated Bay Point, Lafayette, Pacheco, Contra Costa Centre areas, and Kirker Pass Road. Work by site includes: Site 1 - Bay Point applying either an asphalt rubber chip seal covered with a type II slurry seal or applying a type II slurry seal only on various roads; select roads will require a mill and overlay. Site 2 - Lafayette Area is a mill and overlay of three (3) Cul-de-sacs. Site 3 - Pacheco Area placing asphalt rubber chip seal covered with a type II slurry seal, and a mill and overlay on Concord Ave. Site 4 - Contra Costa Centre includes applying a micro-surfacing on various roads. Site 5 - Kirker Pass Road includes placing a micro-surfacing on a portion within the unincorporated area of Concord and a portion within the city of Pittsburg limits. Work in all areas also includes pavement surface preparation including: weed spray, crack sealing, pavement failure repair, edge grinding, and thermoplastic stripe removal; adjusting and setting survey monuments, placement of thermoplastic traffic striping and pavement markings, and traffic signal loop installation. Estimated cost of construction: Base Bid: $5,695,000 Additive Bid 1: $2,345,000 Additive Bid 2: $2,540,000 Additive Bid 3: $1,277,000 Working Days: Base Bid: 92 days Additive Bid 1: 55 additional days Additive Bid 2: 49 additional days Additive Bid 3: 25 additional days Estimated Construction Date: Summer 2023 Project Funding 95% Local Gas Tax, SB1 5% CalRecycle Grant The bidder shall make a "Good Faith Effort", and document this effort, to obtain sub-bid participation by MBE's, WBE's, OBE's, SBE's and LBE's in accordance with the project special provisions to be eligible for award. Bidders that have not attended a pre bid meeting in the last 12 months should attend the County pre bid meeting noted in the Notice to Contractors. The pre bid meeting will include an overview of the Outreach Program requirements and staff will be available to answer your questions. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |