Similar Projects
Last Updated | 01/06/2023 08:36 AM |
Project Title | Hanley Baseball Complex - Phase 1 (Utilities) |
Physical Address | View project details and contacts |
City, State (County) | Central Point, OR 97502 (Jackson County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Park/Playground, Shoreline/Erosion/Drainage, Site Development, Water Lines |
Contracting Method | Bids by Invitation, Competitive Bids |
Project Status | Contract Award, Construction start expected January 2023 |
Bids Due | View project details and contacts |
Estimated Value | $842,163 [brand] Estimate |
Plans Available from | Agency's Affiliate |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | As of January 6, 2023, project was awarded to Visar Construction, Inc., awarded amount is $842,162.50. For Hanley Baseball Complex - Phase 1 (Utilities) This project consists of removal of existing culverts, trenching and excavation, sewer line with laterals, waterline and associated appurtenances including meters, culverts, and trench resurfacing. Bidders must be prequalified in order to be eligible for award. Pre-qualification may be with the City of Central Point, City of Medford, or the Oregon Department of Transportation. If the bidder is disqualified in any of these jurisdictions, the bidder will be ineligible for this contract. Award of contract will not be final until the later of: 1) three business days after the City of Central Point announces Notice of Intent to Award, or 2) the City of Central Point provides a written response to each timely protest, denying the protest and affirming the award. On all projects, work performed by the Contractor's own organization must be at least 30% of the awarded contract amount. Any addenda issued will be posted electronically. COST ESTIMATE: $750,000 - $950,000 *The value for this project is based on a financial range. The value is listed as the highest possible cost from the range provided by a stakeholder or official project document. This is a City funded project. Work shall begin no earlier than December 22nd, 2022 and must be completed by March 31st, 2023 Please direct all questions to Greg Graves at 541-664-3321 (x225) or greg.graves@centralpoint.gov. The deadline for questions is December 9th, 2022. No bid will be received or considered by the City of Central Point unless bidder signs the bid statement. The contract is for public work subject to ORS 279C.800 to 279.870. This project is subject to Oregon prevailing wage rates. The City of Central Point may reject any bid not in compliance with all public bidding procedures and requirements and may reject for good cause any or all bids upon a finding by the City of Central Point that it is in the public interest to do so. |
||||||||||
Details |
|
||||||||||
Bidder's List | View project details and contacts | ||||||||||
Prospective Bidders | View project details and contacts | ||||||||||
Project Documents |
![]() Engineered Spec Sheet ![]() Architectural Plans ![]() Other Documents |