Similar Projects
Last Updated | 02/21/2023 03:34 AM |
Project Title | Sand Hollow North Dam to West Dam Pipeline Installation Project |
Physical Address | View project details and contacts |
City, State (County) | St George, UT 84770 (Washington County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Dam/Tunnel, Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Contract Award, Request for Qualifications, Construction start expected March 2023 |
Bids Due | View project details and contacts |
Estimated Value | $645,584 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | **As of February 20, 2023, project was awarded to Feller Enterprises, awarded amount is $645,583.54.** The contract consists of installing approximately 11,000 feet of owner furnished 24" and smaller ductile iron pipe and appurtenances, furnishing and installing approximately 12,300 feet of 1 1/4 " HDPE communication conduit with pull boxes, five tie-ins to existing pipelines, earthwork for a 500 foot segment of access roadway, and other miscellaneous related work. Bids may be rejected for any of the reasons set forth in Utah Code Annotated, Section 63G-6a-120. |
||||||||
Details |
|
||||||||
Bidder's List | View project details and contacts | ||||||||
Prospective Bidders | View project details and contacts | ||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |