Last Updated | 01/06/2023 11:32 AM |
Project Title | Bull Early Education Center - 2020 Bond - Racine Unified School District |
Physical Address | View project details and contacts |
City, State (County) | Racine, WI 53403 (Racine County) |
Category(s) | Education, Heavy and Highway |
Sub-Category(s) | Elementary School, Sidewalks/Parking Lot, Site Development |
Contracting Method | Competitive Bids |
Project Status | Design Development, Construction start expected May 2027 |
Bids Due | View project details and contacts |
Estimated Value | $1,046,632 [brand] Estimate |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | As of January 6, 2023, a construction manager has been selected and this project is in the planning phase. Information regarding an architect has not been released. Construction is expected to begin in May of 2027 and complete in August of 2027. 2020 Bond to fund $598 million of work over 30 years BULL EARLY EDUCATION CENTER The referendum would provide the funding needed to make the following improvements at Bull: SAFETY & SECURITY: • Updates for ADA-compliant access • Install emergency backup generator LEARNING SPACES: • Expand existing playground INFRASTRUCTURE: • Address building maintenance (lighting, roofing, exterior masonry) • Preventative maintenance for parking lot and concrete The bond was passed and approved by the voters on April 7, 2020. |
||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |