Similar Projects
Reported | 06/10/2021 12:00 AM |
Project Title | Emergency Response for Street Lighting Restoration |
Physical Address | View project details and contacts |
City, State (County) | FL (Miami-Dade County) |
Category(s) | Outdoor Lighting |
Sub-Category(s) | Roadway Lighting |
Contracting Method | Competitive Bids. |
Project Status | Bidding |
Bids Due | View project details and contacts |
Estimated Value | $1,470,000 |
Plans Available from | Agency's Affiliate - 05/06/21 |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Work under this contract includes, but is not limited to the following: Furnishing all supervision, labor, required materials, equipment, tools and performing all operations necessary, including Maintenance of Traffic (MOT) to completely perform Emergency Street Lighting Restoration pursuant to Mayor’s, Governor’s, or President Declaration of Emergency (Declaration of Emergency). The County, at its discretion, may award more than one contract based on the proposals received and the impacts of events associated with the Declaration of Emergency. For additional Work detail, refer to the Miami-Dade County Roadway Lighting Manual, the Public Works Manual of Metropolitan Dade County (Public Works Manual), the Florida Department of Transportation (FDOT) Standard Specifications for Road and Bridge Construction and the National Electric Code (NEC). The Street Lighting Restoration may include but not limited to include the following: 1. The repairs/replacement will include returning the street lighting system to its full operation conditions. 2. Work may entail furnish and install all components associated with the street lighting systems. 3. Contractor must cut, remove and discard any obstacles (trees, fences, etc.) obstructing the right of way within the limits of street lighting facilities in order to perform the work. 4. Replace sidewalk flags damaged during the storm by any of the street lighting components. Any sidewalk repairs must be previously approved by the Engineer, and must comply with all FDOT requirements 5. Measure and certify all work to the Engineer or their designated representative. Take digital pictures with GPS coordinates embedded on them before and after work is performed and submit these files/pictures with each daily work log in print and electronic form. Note post identification, approximate location, severity of damage, and time it took to repaired it. C. All work to be performed will be paid by the included pay items. Any work listed under these provisions without pay item must be included as an incidental to the work repair |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |