Reported | 06/23/2022 12:00 AM |
Project Title | 2022 Green Infrastructure Alley Improvements |
Physical Address | View project details and contacts |
City, State (County) | Maywood, IL (Cook County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Paving/Reconstruction |
Contracting Method | Competitive Bids. |
Project Status | Bidding, Construction Start Expected July 2022 |
Bids Due | View project details and contacts |
Estimated Value | $301,000 [brand] Estimate |
Plans Available from | Municipal Agency |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | This project consists of green alley improvements within the Village of Maywood. The work to be performed will include the removal and replacement of curb and gutter, sidewalks, and garage aprons; excavation of the existing pavement; installation of an aggregate base course; installation of concrete alley pavement; installation of permeable brick pavers and infiltration within the alley pavements; landscaping restoration of disturbed sections of the parkways, and other related work. |
||||||
Details |
|
||||||
Bidder's List | View project details and contacts | ||||||
Prospective Bidders | View project details and contacts | ||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |