Similar Projects
Last Updated | 04/06/2023 02:03 PM |
Project Title | Two-Phase Design and Construction Site Development and Utilities Phases I and II, Tyndall AFB, FL |
Physical Address | View project details and contacts |
City, State (County) | Tyndall AFB, FL 32403 (Bay County) |
Category(s) | Government/Public, Heavy and Highway, Sewer and Water |
Sub-Category(s) | Maintenance, Military Facility, Paving/Reconstruction, Sidewalks/Parking Lot, Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Construction Commenced, Construction start expected March 2023 , Request For Proposals |
Bids Due | View project details and contacts |
Estimated Value | $357,983,153 [brand] Estimate |
Plans Available from | Consultant - 02/20/20 |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | *As of March 22, 2023, construction is underway. A design/builder was awarded on May 17, 2022. Contract Award Date: Apr 29, 2022 Contract Award Number: W9127822C0017 Task/Delivery Order Number: Contractor Awarded Unique Entity ID: R1BYK4E3LAX7 Contractor Awarded Name: LANE CONSTRUCTION CORPORATION, THE Contractor Awarded Address: Cheshire, CT 06410-1212 USA Base and All Options Value (Total Contract Value): $357983153.00 Approximately Date of Solicitation 20 February 2020 This Project Is Advertised On An Unrestricted Basis This Project Is A Request For Proposal (Rfp), Two-phase Design-build Source Selection Solicitation The North American Industry Classification System (Naics) Code For This Project Is 237990, Heavy Civil and Industrial Construction, size standard $39.5m. This project is a Best Value, two-phase design-build solicitation. A detailed project description and overall project performance requirements for this project will be included in the Request For Proposals (RFP) package. The solicitation criteria relies upon industry standards, where allowable, to afford the offeror a degree of design flexibility while meeting certain specific project requirements. The successful Contractor must design and construct a complete and usable project, as described in the RFP documents. One solicitation will be issued covering both phases. Proposals will be evaluated in Phase One to determine which offerors will submit proposals for Phase Two, and an amendment will be issued to those selected offerors. Selection of offerors for involvement in Phase Two will be based on technical approach and performance capability. Detailed project design requirements will then be added by amendment to the solicitation at the start of the Phase Two stage of the Request For Proposals. A maximum of five (5) firms will be invited to participate in the second phase. Estimated Cost Range Project from $250,000,000 to $500,000,000 Design and construct roadways, fencing, lighting, parking, water, wastewater, electrical, storm water, communications and gas throughout Tyndall AFB, FL. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements and other supporting work necessary to make a complete and usable facility. Work includes multiple privatized utility contractors performing utility work for electrical and water performed by Gulf Coast Electric Cooperative (GCEC) and gas performed by Peoples Gas Systems (PGS) in the same general area as this work. This project will demolish existing pavements and utilities associated with this effort. The North American Industry Classification System (NAICS) code for this project is 237990. Field Office: Tyndall Resident Office: POC: Jonathan Carr, 850-283-3856 Project Manager: Brian Dykes, 251-690-3431 Project Engineer: Mark Crawford, 251-690-2684 A/E: Jacobs POC: Daryal Danley daryal.danley@jacobs.com 678-215-1191 Specification Engineer: Marie Klusman, 251-694-3644 Note No. 1: All prospective contractors and their subcontractors and suppliers must be registered in beta.sam.gov before they will be allowed to download solicitation information. Contractors must be registered in the System for Award Management (SAM) at https://www.sam.gov/portal/public/SAM/ prior to award of this contract. Solicitation documents, plans and specifications will only be available via beta.sam.gov. Registration for plans and specifications should be made via beta.sam.gov. If you are not registered, the United States Government is not responsible for providing you with notifications of any changes to this solicitation. The solicitation will be available only as a direct download. This solicitation will not be issued on CD-ROM. Neither telephonic, mailed, nor fax requests will be accepted. Registration should be completed one week prior to the issue date. It is therefore the Contractor's responsibility to monitor the website daily for the solicitation to be posted, and for any posted changes or amendments to this solicitation. The plans and specifications and all notifications of changes to this solicitation shall only be made through this posting and modifications hereto. Plans and specifications will not be provided in a printed-paper format; however, the Government reserves the right to revert to paper medium when it is determined to be in the Government's best interest. NOTE: This solicitation is in .pdf format and requires Adobe Acrobat Reader. Adobe Acrobat Reader may be downloaded free of charge at http://www.adobe.com/products/reader. Note No. 2: All bid forms, bid bonds, and other normal documents required for the bid submittal, including amendments to the bid submittal, shall be electronic format with the proposal. Note No. 3: Critical path method (network analysis system) is required. Note No. 4: For this job, a small business is defined as having average annual receipts of less than $39,500,000 for the past three years. Note No. 5: This solicitation includes bid options which may not be awarded. Note No. 6: All advertisements of Mobile District projects will be through beta.sam.gov. Detailed information on this and other Mobile District Projects (Ordering Solicitations, Points of Contact, Synopsis of Work, etc.) are available on the Internet at: https://www.beta.sam.gov. Address questions concerning downloading of plans/specifications to the Contract Specialist indicated above. Note No. 7: A Contractor Site Visit will be conducted with those offerors advancing to Phase Two. Phase Two offerors will be notified via amendment, as to when and where the site visit will be conducted. Note No. 8: The request for information (RFI) process for bidder inquiries during the advertisement period will be through the ProjNet internet based system, and specifics will be contained in the RFP solicitation package available exclusively from beta.sam.gov. Other forms of communicating RFIs to the Government will not be honored. The Government will try to respond to all questions. However, responses may not be furnished to all questions and particularly those received late in the advertisement period (0-10 days prior to bid opening.) |
||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |