Reported | 11/06/2020 12:00 AM |
Project Title | Hollings Cancer Center Mechanical Equipment Replacement |
Physical Address | View project details and contacts |
City, State (County) | Charleston, SC 29425 (Charleston County) |
Category(s) | Single Trades |
Sub-Category(s) | Mechanical |
Contracting Method | Competitive Bids. |
Project Status | Bidding |
Bids Due | View project details and contacts |
Estimated Value | $3,000,000 to $3,100,000 |
Plans Available from | Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Replace (2) air handling units currently in the HCC 4th floor mechanical room with (1) rooftop air handling unit and (1) air handling unit in the mechanical room. Demolish (1) abandoned roof-mounted air-cooled chiller and associated pumps and piping. Replace (1) water-cooled chiller within mechanical room and associated pumps and piping. Replace (2) cooling tower cells on the roof and associated pumps and piping |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |