Similar Projects
Last Updated | 01/03/2024 02:06 PM |
Project Title | North Heights Waterline Replacement Phase III |
Physical Address | View project details and contacts |
City, State (County) | Sheridan, WY 82801 (Sheridan County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Bidding, Construction start expected March 2024 |
Bids Due | View project details and contacts |
Estimated Value | $1,500,000 [brand] Estimate |
Plans Available from | Agency's Affiliate |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Schedule 1 includes the replacement of all the ductile iron water mainline for the North Heights Drive & Way section. Construction shall include a total of 2,038 LF of 8" PVC mainline, 56 service connections, 3 connections into 8" mainline, abandonment of the existing main and restoration of all surfacing to original conditions. The contractor will have 50 days to complete the bid option once construction of this section begins. Schedule 2 includes replacement of all ductile iron water mainline for the North Heights Road seciton. Construction shall include a total of 863 LF of 12" PVC mainline, 24 service connections, 2 connections into 12" mainline, abandonment of the existing main and restoration of all surfacing to original conditions. The contractor will have 35 days to complete the bid option once construction of this section begins. Schedule 3 includes the replacment of all ductile iron water mainline for the North Heights Avenue section. Construction shall include a total of 790 LF of 12" PVC mainline, 11 service connections, 2 connections into 12' mainline, abandonment of the existing main and restoration of all surfacing to original conditions. The contractor will have 35 days to complete the bid option once construction of this section begins. Schedule 4 includes replacement of all iron water mainline for the North Heights Court section. Construction shall include a total of 385 LF of 8" PVC mainline, 13 service connections, 1 connection into 8" mainline, abandonment of the existing main and restoration of all surfacing to original conditions. The contractor will have 25 days to complete the bid option once construction of this section begins. Temporary water shall be supplied to residents at all times as well as traffic controls to ensure safe travel of local traffic. Water Main (Repair/Replace) Rehabilitation, Waterlines, Water Utilities, Water/Wastewater Infrastructure, Traffic Control. Questions regarding this project should be addressed to: MC2 Engineering & Construction P.C., Taylor Enger, PHONE: 307-673-7350. ADDRESS: 902 N. Main Street, Sheridan, WY 82801 |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |