Similar Projects
Last Updated | 10/02/2023 05:03 PM |
Project Title | Shuler Well Filtration System |
Physical Address | View project details and contacts |
City, State (County) | Williston, SC 29853 (Barnwell County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Lift and Pump Stations, Site Development, Water Lines |
Contracting Method | Competitive Bids |
Project Status | Bidding, Construction start expected November 2023 , Request For Proposals |
Bids Due | View project details and contacts |
Estimated Value | $200,000 [brand] Estimate |
Plans Available from | Civil Engineer |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Installation of 750-gpm water filtration system including site work, concrete pad, canopy (Add Alternate), backwash holding tank, 915 linear feet of gravity sewer, electrical, fencing and appurtenances Time allotted for construction is 360 consecutive calendar days for substantial and final completion. Consideration will be given for issuing the Notice to Proceed based upon anticipated delivery of materials. Proposals for the complete work in one general contract shall be made on the proposal form provided and shall contain prices in words and figures for the work bid on. This is a Section 3 Covered Project under the HUD Act of 1968 and Section 3 Residents and Business Concerns are encouraged to apply. The OWNER is committed to providing all persons with equal access to its services, programs, activities, education, and employment regardless of race, color, national origin, religion, sex, familial status, disability or age All Bidders must have a State of South Carolina Contractors WL4, WP4 or higher License No submitted bid may be withdrawn after the scheduled closing time for receipt of bids for a period of ninety (90) days All proposals shall be accompanied by a Bid Bond drawn in favor of the Town of Williston, in the amount of at least 10% of the lump sum bid for the complete work; such Bid Bond representing that the Bidder, if awarded the contract, will promptly enter into a contract and furnish Performance Bond and Payment Bond as provided by law and approved by the Attorney for the Town of Williston. Each bond shall be equal to 100% of the contract amount. The Bid Bond shall be forfeited to the Town of Williston as liquidated damages if the Bidder fails to execute the contract and provide Performance and Payment Bonds within 10 days after being notified that he has been awarded the contract. Upon receipt of all documents in undamaged condition within 30 days after the date of opening of bids, half of the deposit will be refunded. The Owner reserves the right to reject any or all bids and to waive informalities |
||||||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |