Similar Projects
Last Updated | 02/09/2022 08:10 AM |
Project Title | Albany Street Widening Phase II from 23rd Street to 37th Street |
Physical Address | View project details and contacts |
City, State (County) | Broken Arrow, OK 74011 (Tulsa County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Paving/Reconstruction, Sidewalks/Parking Lot |
Contracting Method | Competitive Bids. |
Project Status | Results |
Bids Due | View project details and contacts |
Estimated Value | $2,700,000 |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Phase II project includes: construction of approximately 4,456 feet of asphalt mill & overlay with 1,778 feet of asphalt roadway widening from 2-lanes to 5-lanes as well as 2,678 feet of asphalt roadway widening from 2-lanes to 2 or 3-lanes with 4' asphalt shoulders. The project also includes construction of approximately 7,400 linear feet of concrete sidewalk, approximately 2,400 linear feet of concrete curb and gutter, both asphalt and concrete driveways, enclosed storm sewers, and drainage culverts. The project is along East Albany Street between 23rd Street and 37th Street in Broken Arrow, OK. |
||||||||
Details |
|
||||||||
Bidder's List | View project details and contacts | ||||||||
Prospective Bidders | View project details and contacts | ||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |