Last Updated | 02/10/2022 12:08 PM |
Project Title | East Wallkill Emergency Operations Center |
Physical Address | View project details and contacts |
City, State (County) | New Paltz, NY 12561 (Ulster County) |
Category(s) | Government/Public |
Sub-Category(s) | Misc. Buildings |
Contracting Method | |
Project Status | Construction Commenced first quarter 2021, Construction Completion Expected June 2022, No Sub Bids Needed |
Bids Due | View project details and contacts |
Estimated Value | $7,025,000 |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Site - $975,000.00 General Construction - $3,850,000.00 Plumbing - $375,000.00 Mechanical - $975,000.00 Electrical - $850,000.00 East of Wallkill Emergency Operations Center Shelter Project consists of the following: Demolition of the existing metal building on site, interconnection of the 911 Memorial, and construction of a new facility that will serve the Village of New Paltz as well as the Town of New Paltz. This project calls for the design and construction of a new 14,290 square foot facility, including an eight-bay firehouse and road and parking improvements. Additionally, the expanded facility will include an emergency operations center that will be used as a command center and staging area by police, fire, national guard and Federal Emergency Management Agency personnel as needed during future disaster events. The existing substation will be demolished by the Village. |
||||||||||||||||||||||||||||||||
Details | 14,290 SF New Construction.
|
||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||