Last Updated | 12/03/2022 07:32 PM |
Project Title | Monticello Pump Station Elimination |
Physical Address | View project details and contacts |
City, State (County) | Louisville, KY 40202 (Jefferson County) |
Category(s) | Heavy and Highway, Sewer and Water |
Sub-Category(s) | Lift and Pump Stations, Site Development |
Contracting Method | Competitive Bids |
Project Status | Results, Construction start expected December 2022 |
Bids Due | View project details and contacts |
Estimated Value | $339,960 [brand] Estimate |
Plans Available from | Agency's Affiliate |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | This contract provides for the installation of approximately 581 linear feet of 10-inch sewer 35 of concrete encasement 4 sanitary manholes; tie into existing sewers decommissioning of one pump station (Monticello Place) and appurtenant work. The project is generally located between Rivanna Drive and Jo Court. All work shall be done in accordance to MSDs Standard Specifications. The Engineers Construction Cost Estimate for this project is between $150,000.00 and $350,000.00. The Project Manager for this Invitation to Bid is Quinn Corcoran. All inquiries and questions prior to the bid opening shall be Directed, in writing, to MSDs Project Manager, Quinn Corcoran at quinn.corcoran @louisvillemsd.org . Questions received less than ten days prior to the date for opening of bids may not be answered. Only answers by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. All inquiries and questions between the bid opening and the contract awarding shall be directed, in writing, to MSD's Chief Engineer, David Johnson, P.E. *Project information has been obtained through a public capital improvement plan (CIP). A CIP is a financial schedule for short- and long-range projects which is updated regularly. Information listed in the CIP often evolves based on funding availability and the project details, including timeline and value, are subject to change. The content management team will continue to pursue additional details as they become available. *The value for this project is based on a financial range. The value is listed as the highest possible cost from the range provided by a stakeholder or official project document. |
||||||||||||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |