Similar Projects
Last Updated | 07/11/2023 12:43 PM |
Project Title | Roadway Reconstruction and Traffic Signal Installation on Gross Point Road |
Physical Address | View project details and contacts |
City, State (County) | Skokie, IL 60077 (Cook County) |
Category(s) | Heavy and Highway, Outdoor Lighting |
Sub-Category(s) | Maintenance, Paving/Reconstruction, Roadway Lighting, Site Development |
Contracting Method | Bids by Invitation, Competitive Bids |
Project Status | Contract Award, Request for Qualifications, Construction start expected May 2023 |
Bids Due | View project details and contacts |
Estimated Value | $6,618,000 [brand] Estimate |
Plans Available from | State Agency |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | As of July 11, 2023, the project has been awarded. A timeline for construction has not been confirmed. Roadway reconstruction and traffic signal installation on Gross Point Road from Old Orchard Road to Gold Road in Skokie. Region 1 District 1 Federal Project # V57S(558) County(s) Cook Key Route(s) FAU 3520 Marked Route(s) Gross Point Road Section(s) 08-00279-00-FP (SKOKIE) State Job #(s) C-91-042-10 PPS #(s) 1-11023-0017 1-20780-0000 1-20780-0010 Completion Date: 110 Working Days Questions not accepted as of February 28, 2023 04:30 PM. Questions directed to: IDOT Contracts Office Harry R. Hanley Building Room 326 2300 South Dirksen Parkway Springfield, IL 62764 (217) 782-7806 Fax: (217) 785-1141 TDD: (217) 524-4875 DOT.DE-Contracts@illinois.gov Unless otherwise indicated, a proposal guaranty is required by bid bonds, cashier's check or properly certified check for not less than 5 (five) percent of the bid amount. If the proposal is accepted and the bidder is declared "not responsive," it is hereby agreed that the amount of the proposal guaranty will become the property of the State of Illinois and shall be considered as payment of damages due to the delay and other causes suffered by the State because of the failure to adhere to the procedures required. Otherwise, the bid bond will become void or the proposal guaranty check will be returned to the bidder. Contractors who desire to become prequalified or to renew their prequalification for this letting must file with the Department of Transportation, Bureau of Construction, Room 322, 2300 South Dirksen Parkway, Springfield, Illinois 62764, a Contractor's Statement of Experience and Financial Condition no later than 4:30 PM prevailing local time, February 17, 2023. A contractor will not be prequalified for this letting unless the statement is received before the time and day established. Department reserves the right to reject any and all bids, to waive minor or immaterial irregularities, informalities or technicalities, to advertise for new bids, or to request confirmation or clarification from any bidder regarding a bid. ILDOT - 077 - Roadway Reconstruction and Traffic Signal Installation on Gross Point Road *Information regarding subcontractor bidding has not been disclosed to the content management team at this time. Interested subcontractors should contact the general contractor directly for more information. |
||||||
Details |
|
||||||
Bidder's List | View project details and contacts | ||||||
Prospective Bidders | View project details and contacts | ||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |