Reported | 06/29/2022 10:08 AM |
Project Title | Marina Dredging And Dock Upgrades - C14402010 - City of Petaluma |
Physical Address | View project details and contacts |
City, State (County) | Petaluma, CA (Sonoma County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Dock/Pier/Marine, Dredging |
Contracting Method | Competitive Bids. |
Project Status | Conceptual Design, Construction Start Expected March 2023 |
Bids Due | View project details and contacts |
Estimated Value | $4,895,000 [brand] Estimate |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Recovering the full operational water depth for boating safety, navigation, and Marina operations will facilitate higher tenant occupancy and capacity, which is the primary goal for this project. Unlike the Petaluma River Channel, the Marina is not in the federal navigation channel, so it was not part of the recently completed U.S. Army Corps of Engineers (USACE) river dredging project. Currently, a large percentage of Marina boating slips do not have adequate water depth to accommodate vessels and are thus vacant and unleasable. This project involves dredging Petaluma's Marina to restore it to its full design depth. Additionally, the project includes repairs to the floating docks and gangways at both the Marina and the Turning Basin, as well as supplemental dredging in the Turning Basin under the docks (which was not allowed in the USACE dredge project). While funding is largely undetermined, there is a construction target of FY 23-24 to complete the project before the California Fish and Wildlife permit expires. This project is included in the City of Petaluma's FY 2022-2027 Capital Improvement Plan (CIP). As of June 28, 2022, information regarding a design team or a general contractor is not available. Construction is anticipated in FY 2023-2024.* *Project information has been obtained through a public capital improvement plan (CIP). A CIP is a financial schedule for short- and long-range projects which is updated regularly. Information listed in the CIP often evolves based on funding availability and the project details, including timeline and value, are subject to change. The content management team will continue to pursue additional details as they become available. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |