Last Updated | 04/12/2023 10:17 AM |
Project Title | Replace 30 Ton Chiller, B1 |
Physical Address | View project details and contacts |
City, State (County) | Virginia Beach, VA 23460 (Virginia Beach City County) |
Category(s) | Government/Public |
Sub-Category(s) | Military Facility |
Contracting Method | Competitive Bids |
Project Status | All Bids Received, Selection Underway, Construction start expected April 2023 |
Bids Due | View project details and contacts |
Estimated Value | $250,000 [brand] Estimate |
Plans Available from | Plan Holders |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | NAVFAC RFP NO: N40085-23-R-2610 eProjects WO#: 1743760 Location ofthe work: JEBLCFS, Little Creek Site, Virginia Beach, VA The Contractor shall provide supervision, labor, material and equipment required to perform all work for the following project: Replace existing 30-ton air-cooled chiller with 25-ton air-cooled chiller. All work shall be done in a manner to provide a complete, usable and finished end product. Pre-Proposal Inquiries (PPIs) submitted in writing via Attachment F, PPI Form to Gina Moriarty at gina.c.moriarty.civ@navy.mil no later than Monday, 27 February 2023 at 1400 in order to process all inquiries by the proposal date. MAGNITUDE: Estimated between $100,000 and $250,000. *The value for this project is based on a financial range. The value is listed as the highest possible cost from the range provided by a stakeholder or official project document. Provide and install a new air-cooled 25-ton chiller following the basis of design listed below: Air-Cooled Scroll Packaged Chiller Manufacturer's Authorized Startup Included 460 volt 3 phases 60 hertz Extra efficiency/performance Full factory refrigerant charge (HFC-410A) With factory installed freeze protection Refrigerant isolation valves (discharge valve) UL listed to US and Canadian safety standard ASHRAE 90.1 all versions up to 2016 AHRI certified Factory installed flow switch - set point 60 cm/sec Phase Reversal Protection Std cooling (40 to 65F/4.44 to 18C) Grooved pipe connection Factory insulation 0.75" Performance based on water Wide ambient (0 to 125F/-18 to 52C) CompleteCoat lanced aluminum fins Across the line starter/direct on line Single point connection main line unit power-ancillary items require other power Circuit breaker Enclosure type UL 1995 rated for outdoor applications BACnet interface (controls by others) Dual high head pump (no integral buffer tank) Pump flow ctrl by var speed drive Default A short circuit rating Elastomeric isolators (Fld) With water strainer factory installed Super quiet Architectural louvered panels 5 year compressor parts Startup, checkout, owner training, 1st year labor warranty and refrigerant warranty Provide chiller branch circuit to include new stainless steel fused disconnect, conduit (rigid and liquid tight), conductors, fittings, junction box, and supports to chiller power point connection. Provide fuses sized in accordance with the chiller manufacturer's maximum overcurrent specifications. Provide new slotted metal channel mounting and straps for disconnect. Provide complete electrical circuit for the new chiller barrel heaters and control voltage as required. Provide new steel chilled water piping, observe and maintain proper chilled water flow from the building to the chiller. Provide new heat trace with controls, Install new electrically operated three-way change over valves in the overhead of the mechanical room to include one valve and actuator on the supply, return, and bypass piping. Tie new actuators into existing DDC system. Reconfigure piping as required to install valves. Reinstall chiller DDC. Install new pressure reducing valve and expansion tank for the chilled water system, located in overhead of mechanical room. Install new circulating pump, CP-2, in the overhead of the mechanical room. Match existing pump GPM, horsepower, and voltage. |
||||||||||||||||||||||||||||||||||||
Details |
|
||||||||||||||||||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |