Similar Projects
Last Updated | 05/09/2023 03:02 PM |
Project Title | Angola High School Locker Rooms and Tennis Improvements Rebid |
Physical Address | View project details and contacts |
City, State (County) | Angola, IN 46703 (Steuben County) |
Category(s) | Entertainment/Recreation, Heavy and Highway |
Sub-Category(s) | Athletic Facility, Site Development |
Contracting Method | Construction Management - CM at Risk, Competitive Bids |
Project Status | Bidding, Construction start expected May 2023 |
Bids Due | View project details and contacts |
Estimated Value | $3,500,000 [brand] Estimate |
Plans Available from | Copy Center |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Project Description: Project includes The construction of two (2) new freestanding sports locker room structures; one (1) is a single-story football locker room building (approximately 15,000 square feet) and one (1) is a baseball/softball locker room building (approximately 2,500 square feet). The project also includes construction of an approximately 275 car parking lot and construction of new discus courts and shot-put courts, in addition to the construction of a 2-story covered pavilion and fencing replacement at the existing tennis courts. Project consists of 3 Prime Bidders General Trades Mechanical Electrical Bid security shall be submitted with each bid in the amount of 5 percent of the bid amount. Bid security shall be a certified check or bid bond and shall be the bidder's guarantee that said bidder will, if the contract is awarded to said bidder, execute within ten (10) days of acceptance of his bid, a Contract for the work bid upon. All bid bonds shall be made payable to the Owner and be executed by a surety company authorized to do business in the State of Indiana. No bids may be withdrawn for a period of 60 days after opening of bids. Owner reserves the right to reject any and all bids and to waive informalities and irregularities. The successful bidders will be required to furnish Performance and Payment Bonds for one hundred percent (100%) of their contract amount prior to execution of contracts. Bonds shall be in full force and effect for a period of at least 12 months after the date of final completion and acceptance of the longest guarantee provided under the contractor's contract. Should the contractor's bonding company default; the contractor will be responsible for securing a new bond within fourteen (14) calendar days. |
||||||||||||||||||||
Details | 17,500 SF.
|
||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |