Similar Projects
Last Updated | 11/21/2022 01:43 AM |
Project Title | Replace Building 123 Mental Health Emergency Generator and Switchboard |
Physical Address | View project details and contacts |
City, State (County) | West Milwaukee, WI 53214 (Milwaukee County) |
Category(s) | Single Trades |
Sub-Category(s) | Electric |
Contracting Method | Competitive Bids |
Project Status | Sub-Bidding, Construction start expected November 2022 |
Bids Due | View project details and contacts |
Estimated Value | $2,000,000 [brand] Estimate |
Plans Available from | Agency's Affiliate |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | VA Project Number: 695-21-104: Replace Building 123 Mental Health Emergency Generator and Switchboard Price Range: $1,000,000 to $2,000,000. Base Bid: Contractor shall provide for and furnish all labor, materials, equipment, qualified supervision, and other items designated in this contract in accordance with the specifications and drawings to complete Project # 695-21-104 Replace Building 123 Mental Health Emergency Generator and Switchboard at Clement J. Zablocki VA Medical Center, 5000 West National Avenue Milwaukee, WI. The project involves replacing building 123 mental health emergency generator and electrical distribution equipment. All work shall be completed within 360 calendar days after receiving Notice to Proceed. CLIN 0001: Base Bid LUMP SUM: _______________________________ ************************************************************************************* NOTICE TO BIDDERS: Award will be made to the responsible bidder who submitted the lowest responsive bid. NOTICE TO BIDDERS: At times, the contractor will be working in occupied buildings and the hospital. Work plans for VA review/approval are required before any work can begin associated with any of the tasks. Outages and shut-downs will need to take this information into account. Off-shift scheduling (nights/weekends) is required for outages, shutdowns, and work directly impacting patient care. The contractor will be required to keep all other non-impacted roads, walks and entrances to grounds, parking, and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Submittals regarding staging of equipment, crane placement, storage of supplies, etc. are required. Off-hours and/or week-end deliveries of construction equipment or materials may be required. NOTICE TO BIDDERS: An approved cost-loaded, Critical Path Method (CPM) construction schedule is required prior to commencement of construction. See specifications for details. CPM schedule shall be approved by the Contracting Officer or the Contracting Officer's Representative. See specifications for details. NOTICE TO BIDDERS: Additional information regarding the general and specific scope of work is defined in the specifications and drawings. This BID SCHEDULE is in addition to and augments the specifications and drawings. ONLY ONE AWARD WILL BE MADE AS A RESULT OF THIS SOLICITATION. Page 3 of 5836C25222B0028 Contracting Officer's Special Instructions as follows: After compiling all required information, submit the information in accordance with Block 13 of the SF 1442 (page 1 of this solicitation). Return the original and specified number of copies to the issuing office listed in Block 8 of the SF 1442 (page 1 of this solicitation). INQUIRIES: Written requests for information or clarifications to solicitation documents are requested to be submitted to the Contract Specialist at Kristine.Sutton@va.gov AND Contracting Officer at Stacy.Hoover2@va.gov no later than August 23, 2022. Requests received after this deadline may not be addressed. Telephone inquiries will not be accepted. Inquiries and all correspondence concerning this solicitation document should be submitted in writing to the Contract Specialist and Contracting Officer. YOU ARE INSTRUCTED SPECIFICALLY TO CONTACT ONLY THE CONTRACT SPECIALIST AND CONTRACTING OFFICER ISSUING THE SOLICITATION ABOUT ANY ASPECT OF THIS REQUIREMENT PRIOR TO CONTRACT AWARD. BID OPENING INFORMATION: The bid opening will be conducted on September 8, 2022 at 11:30am local time at the below address: Department of Veterans Affairs Great Lakes Acquisition Center 115 S. 84 th St. 1 st Floor Milwaukee, WI 53214-1476 CONTRACTOR'S SIGNATURE: In accordance with Federal Acquisition Regulations Part 4, contractual documents (e.g. bids, proposals, awards, modifications, etc.) shall be completed and signed by the Contractor as follows: (a) Individuals. A contract with an individual shall be signed by that individual. A contract with an individual doing business as a firm shall be signed by that individual, and the signature shall be followed by the individual's typed, stamped, or printed name and the words ", an individual doing business as _________" [insert name of firm]. (b) Partnerships. A contract with a partnership shall be signed in the partnership name. Before signing for the Government, the contracting officer shall obtain a list of all partners and ensure that the individual(s) signing for the partnership have authority to bind the partnership. (c) Corporations. A contract with a corporation shall be signed in the corporate name, followed by the word "by" and the signature and title of the person authorized to sign. The contracting officer shall ensure that the person signing for the corporation has authority to bind the corporation. (d) Joint venturers. A contract with joint venturers may involve any combination of individuals, partnerships, or corporations. The contract shall be signed by each participant in the joint venture in the manner prescribed in paragraphs (a) through (c) of this section for each type of participant. When a Page 4 of 5836C25222B0028 corporation is participating, the contracting officer shall verify that the corporation is authorized to participate in the joint venture. (e) Agents. When an agent is to sign the contract, other than as stated in paragraphs (a) through (d) of this section, the agent's authorization to bind the principal must be established by evidence satisfactory to the contracting officer. *The value for this project is based on a financial range. The value is listed as the highest possible cost from the range provided by a stakeholder or official project document. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |