Similar Projects
Last Updated | 05/03/2021 09:37 AM |
Project Title | SR 45 Corridor Improvements Elevated Water Tank |
Physical Address | View project details and contacts |
City, State (County) | Lordstown, OH (Trumbull County) |
Category(s) | Sewer and Water |
Sub-Category(s) | Storage/Water Tanks |
Contracting Method | Competitive Bids. |
Project Status | Results |
Bids Due | View project details and contacts |
Estimated Value | $16,155,000 |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | A. The bid documents contain bid forms for two (2) contracts. The bidder must bid both contracts. B. Contract A - 3,000,000 gallon elevated composite water tank construction completion date by October 27, 2023 with an Alternate for a December 30, 2022 completion date. Opinion of Probable Construction Cost: Base - $6,800,000.00 Opinion of Probable Construction Cost: Base and Alternate - $7,405,000.00 C. Contract B - 4,000,000 gallon elevated composite water tank construction completion date by October 27, 2023 and an Alternate for a December 30, 2022 completion date. Opinion of Probable Construction Cost: Base - $8,585,000.00 Opinion of Probable Construction Cost: Base and Alternate - $9,355,000.00 |
||||||||||||||
Details |
|
||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||
Project Documents |
![]() Engineered Spec Sheet ![]() Architectural Plans ![]() Other Documents |