Similar Projects
Reported | 07/30/2020 09:21 AM |
Project Title | North Carolina Zoo Baboon Holding, African Pavilion Demo and Zoofari |
Physical Address | View project details and contacts |
City, State (County) | Asheboro, NC 27203 (Randolph County) |
Category(s) | Animal/Plant/Fish Facility |
Sub-Category(s) | Animal/Plant/Fish Facility |
Contracting Method | |
Project Status | Construction Commenced February 2020, No Sub Bids Needed |
Bids Due | View project details and contacts |
Estimated Value | $6,875,000 |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Packages: 02A Selective and Building Demolition, 03A Complete Concrete, 04A Masonry, 05A Structural and Misc. Steel, 06B Carpentry and Casework, 07A Roofing and Accessories, 08B Doors/Frames Hardware, 08D Windows and Glazing, 09A Drywall, 09E Floor - Epoxy, 09F Painting, 10A Specialties, 18B General Works, 22A Plumbing Systems, 23A Mechanical Systems, 26A Electrical Systems, 31A Complete Sitework, 32B Site Fencing and Gates. TRADE PACKAGES - 02A Demolition, 02B Site Electrical, 02C Mechanical, 03A Concrete, 04A Masonry, 05A Structural Steel, 05C Misc. Steel , Handrails, Gates and Fences, 06A Carpentry, 07A Roofing, 08B Passage Door Assemblies, 08D Glass Assemblies, 09A Drywall Assemblies, 09E Floor Coverings, 09F Painting and Wall Coverings, 10A Specialties, 18A General Works, 21A Plumbing Systems, 23A HVAC Systems, 26A Electrical Systems, 31A Complete Sitework. 4,000 square foot, Loadbearing CMU structure to house the baboons. The building is fully air conditioned and contains food preparation areas, keeper office and work space, bath and shower facilities. The Baboon Temporary Wall will include installing a new wall in existing exterior holding area to separate the Baboons from the old and new facilities. The Zoofari Road and Gates Construct will entail a new road and gates around the Zoofari exhibit. The African Pavilion Demolition will include demolishing the existing African Pavilion leaving a partial structure to house the Baboon exterior exhibit and Regrade area and install new walks, overlooks and handrails. May 21,2020 Packages to Include: 06B Carpentry and Casework, 09E Flooring Epoxy, 09F Painting, 10A Specialties |
||||||||||||||||||
Details |
|
||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |