Project Title | Bridge Replacement Br. No. W-07-002 (Steel) Route 67 (Main Street) over the Quaboag River |
Physical Address | View project details and contacts |
City, State (County) | Warren, MA 01083 (Worcester County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Bridge |
Contracting Method | Competitive Bids. |
Project Status | Results |
Bids Due | View project details and contacts |
Estimated Value | $3,076,000 |
Plans Available from | |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | "1.000","Ls","Schedule Of Operations - Fixed Price $26,500.00","100." "80.000","Ft","Pressure Injection Of Cracks","107.855" "4.000","Ea","Remove And Reset Ornamental Light Posts","107.991" "1.000","Ea","Remove, Clean And Reset Memorial Plaque","107.992" "1.000","Ls","Demolition Of Superstructure Of Bridge No. w-07-002 (1aa)","114.1" "304.000","Cy","Earth Excavation","120." "110.000","Cy","Concrete Excavation","127." "10.000","Cy","Reinforced Concrete Excavation","127.1" "3.000","Cy","Reinforced Concrete Excavation For Repairs","127.12" "9.000","Sy","Reinforced Concrete Deck Excavation (Full Depth)","127.4" "2.000","Cy","Reinforced Concrete Deck Excavation (Partial Depth)","127.41" "150.000","Cy","Bridge Excavation","140." "32.000","Cy","Test Pit For Exploration","141.1" "17.000","Cy","Class b Trench Excavation","142." "5.000","Cy","Ordinary Borrow","150." "118.000","Cy","Gravel Borrow","151." "10.000","Cy","Gravel Borrow For Bridge Foundation","151.1" "150.000","Cy","Gravel Borrow For Backfilling Structures And Pipes","151.2" "2.000","Cy","Controlled Density Fill - Non-Excavatable","153.1" "46.000","Cy","Sand Borrow","154." "130.000","Ft","Crushed Stone For Underdrain","156.4" "259.000","Sy","Fine Grading And Compacting - Subgrade Area","170." "1.000","Ls","Inspection And Testing For Asbestos","182.1" "230.000","Ft","Removal Of Asbestos","182.2" "2.000","Ea","Special Catch Basin","201.3" "4.000","Ea","Drainage Structure Adjusted","220." "4.000","Ft","Drainage Structure Rebuilt","220.2" "1.000","Ea","Drainage Structure Change In Type","220.3" "1.000","Ea","Sanitary Structure Adjusted","220.7" "1.000","Ea","Frame And Cover","221." "6.000","Ea","Frame And Grate - Massdot Cascade Type","222.1" "5.000","Ea","Frame And Grate (Or Cover) Removed And Discarded","223.2" "5.000","Cy","Removal Of Drainage Structure Sediment","227.3" "293.000","Ft","Removal Of Drainage Pipe Sediment","227.31" "74.000","Ft","18 Inch Reinforced Concrete Pipe","241.18" "130.000","Ft","8 Inch Perforated Corrugated Metal Pipe-18 Gage (Subdrain)","261.08" "247.000","Ft","Furnish And Install 10 Inch Diameter Water Pipe","303.101" "4.000","Ea","10 Inch Gate And Gate Box","350.10" "3.000","Ea","Gate Box Adjusted","358." "13.000","Cy","Dense Graded Crushed Stone For Sub-Base","402." "1270.000","Sy","Pavement Micromilling","415." "116.000","Ton","Superpave Surface Course – 9.5 (Ssc – 9.5)","450.22" "155.000","Ton","Superpave Intermediate Course - 12.5 (Sic -12.5)","450.31" "25.000","Ton","Superpave Base Course - 37.5 (Sbc - 37.5)","450.42" "34.000","Ton","Superpave Bridge Surface Course - 9.5 (Ssc-b - 9.5)","450.60" "36.000","Ton","Superpave Bridge Protective Course - 9.5 (Spc-b - 9.5)","450.70" "53.000","Ton","Hma For Patching","451." "110.000","Gal","Asphalt Emulsion For Tack Coat","452." "1432.000","Ft","Hma Joint Sealant","453." "55.000","Ton","Asphalt Mixtures For Temporary Work","472." "55.000","Ft","Granite Curb Type Va4 - Straight","504." "20.000","Ft","Granite Transition Curb For Wheelchair Ramps - Straight","509." "3.000","Ea","Granite Curb Inlet - Straight","514." "195.000","Ft","Curb Removed And Reset","580." "10.000","Ft","Guardrail, Tl-3 (Single Faced)","620.13" "1.000","Ea","Trailing Anchorage","627.1" "2.000","Ea","Transition To Bridge Rail","628.24" "96.000","Ft","Highway Guard Removed And Discarded","630.2" "150.000","Ft","Temporary Fence","657." "123.000","Ft","Temporary Fence Removed And Reset","657.5" "10.000","Ft","Chain Link Fence Removed And Stacked","665." "7.000","Ea","Silt Sack","697.1" "70.000","Sy","Geotextile Fabric For Subsurface Drainage","698.2" "190.000","Sy","Cement Concrete Sidewalk","701." "43.000","Sy","Cement Concrete Sidewalk At Driveways","701.1" "1.000","Ea","Sign Post Removed And Stacked","734.52" "33.000","Mo","Engineers Field Office And Equipment (Type a)","740." "1.000","Ls","Mobilization","748." "25.000","Cy","Loam Borrow","751." "25.000","Sy","Wetland Seed","755.65" "90.000","Sy","Seeding","765." "167.000","Sy","Seeding - Roadside Riverbank - Part Shade Mix","765.55" "720.000","Ft","Sediment Control Barrier","767.121" "111.000","Ft","Pavement Milling Mulch Under Guard Rail","769." "1.000","Ls","Temporary Traffic Control Signal","816.81" "1.000","Ls","Remove And Relocate Utility Pole With Luminaire","821.99" "8.000","Sf","Warning-Regulatory And Route Marker - Aluminum Panel (Type a)","832." "1280.000","Hr","Roadway Flagger","850.41" "520.000","Sf","Safety Signing For Traffic Management","852." "2.000","Ea","Portable Breakaway Barricade Type Iii","853.1" "205.000","Ft","Temporary Barrier (Tl-2)","853.2" "435.000","Ft","Temporary Barrier Removed And Reset","853.21" "260.000","Ft","Temporary Barrier - Limited Deflection (Tl-3)","853.33" "2.000","Ea","Temporary Impact Attenuator Removed And Reset","853.501" "2.000","Ea","Temporary Impact Attenuator Unidirectional, Redirective (Tl-3)","853.63" "2170.000","Ft","Temporary Paving Markings - 6 Inch (Painted)","854.016" "40.000","Ft","Temporary Paving Markings - 6 Inch (Tape)","854.036" "437.000","Sf","Pavement Marking Removal","854.1" "5760.000","Day","Reflectorized Drum","859." "1200.000","Day","Reflectorized Drums With Sequential Flashing Warning Lights","859.1" "55.000","Sf","Pavement Arrows And Legends Refl. White (Thermoplastic)","864.04" "1195.000","Sf","Preformed Thermoplastic Bike Lane Markings - Green","865.11" "722.000","Ft","6 Inch Wet Reflective Recessed White Line (Polyurea)","868.206" "640.000","Ft","6 Inch Wet Reflective Recessed Yellow Line (Polyurea)","869.206" "4.000","Ea","Traffic Sign Removed And Stacked","874.4" "5.000","Cy","3000 Psi, 1.5 Inch, 470 Cement Concrete","903." "3.000","Cy","4000 Psi, 3/8 Inch, 660 Cement Concrete","905." "150.000","Sf","Cementitious Mortar For Patching","909.2" "85.000","Bag","Rapid Set Cement","909.99" "500.000","Lb","Steel Reinforcement For Structures","910." "1.000","Ls","Temporary Support Of Excavation","950.11" "1980.000","Sf","Concrete Protective Coating","964.21" "80.000","Ton","Dumped Riprap","983." "1.000","Ls","Control Of Water - Structure No. w-07-002 (1aa)","991.1" "1.000","Ls","Temporary Protective Shielding Outside Fascia Beams Bridge No. w-07-002 (1aa)","994.011" "1.000","Ls","Temporary Protective Shielding Between Fascia Beams Bridge No. w-07-002 (1aa)","994.012" "1.000","Ls","Bridge Superstructure, Bridge No.w-07-002 (1aa)","995." |
||||||||||||||||||||
Details |
|
||||||||||||||||||||
Bidder's List | View project details and contacts | ||||||||||||||||||||
Prospective Bidders | View project details and contacts | ||||||||||||||||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |