Last Updated | 03/29/2023 02:02 PM |
Project Title | English Brook and Camp 12 Culverts |
Physical Address | View project details and contacts |
City, State (County) | Salamanca, NY 14779 (Cattaraugus County) |
Category(s) | Heavy and Highway |
Sub-Category(s) | Shoreline/Erosion/Drainage, Site Development |
Contracting Method | Competitive Bids |
Project Status | Bidding, Construction start expected April 2023 |
Bids Due | View project details and contacts |
Estimated Value | $2,144,186 [brand] Estimate |
Plans Available from | Agency's Affiliate |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | Question Deadline :- 02-23-2023 3:00 pm Removal and replacement of the existing culvert, substructure, wingwalls, and installation of new structure with H-pile foundation system and stone masonry work as detailed. Restoration work will include roadway and side embankment replacement to match pre-construction conditions. Camp 12 Culverts - install two new box culverts at existing waterways to provide access from ASP Rte. 2 Camp 12. Work incudes trail/road resurfacing, excavation and embankment work, storm drainage improvements, and guiderail installation. Culverts will include form liner on exterior. Service-Disabled Veteran-Owned Set Aside: No Minority Owned Sub-Contracting Goal: 0% Women Owned Sub-Contracting Goal: 0% Service-Disabled Veteran-Owned Business Contracting Goal: 0% Contract term: 240 days The project cost estimate is $1,584,833.00 to $2,144,186.00. Liquidated Damages :- $1,750.00 day Scope of Work English Brook Culvert is located on ASP Route 1 nearly 2 miles north of ASP Rte. 3 in the Quaker area of Allegany State Park. This is a reconstruction project consisting of the removal and replacement of the roadway arch culvert over English Brook. This is considered a historic structure by State Historic Preservation Office (SHPO) and is being replaced in-kind to the greatest extent practicable. The new structure is a similar arch culvert including concrete wingwalls and headwalls to be lined with stone veneer to represent the aesthetics of the existing structure. Roadside kneewalls are to be built from existing stone salvaged from the structure removal. Work includes new guiderail, underdrain, storm drainage improvements, embankment, and full roadway section replacement. The culvert base footers are to be built on steel H-piles. Camp 12 is located approximately 3-4-mile north of the intersection of ASP Route 2 and France Brook Road on the east side of Allegany State Park. This is a new-build of two box culverts to span Red House Brook and a separate swale near the Camp 12 area, which will provide direct access to Camp 12 from ASP Route 2. Both culverts will be four-sided box structures. The floor of each culvert will be buried below existing stream elevations to provide a natural bottom condition to comply with environmental permit guidance. The new structures will include concrete wingwalls and headwalls to be lined with form-liner intended to match aesthetics of the natural stone in the surrounding areas of the Park. Work includes new timber-faced guiderail, embankment, natural roadway resurfacing, and storm drainage improvements. |
||||||
Details |
|
||||||
Bidder's List | View project details and contacts | ||||||
Prospective Bidders | View project details and contacts | ||||||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |