Similar Projects
Reported | 02/09/2022 12:00 AM |
Project Title | Florence Major Maintenance Project Early Bid Package #1 - Doors, Frames & Hardware |
Physical Address | View project details and contacts |
City, State (County) | Florence, OR 97439 (Lane County) |
Category(s) | Single Trades |
Sub-Category(s) | Windows/Doors |
Contracting Method | Competitive Bids. |
Project Status | Request for Proposals (RFPs), Construction Start Expected April 2022, Construction Completion Expected December 2022 |
Bids Due | View project details and contacts |
Estimated Value | $6,000,000 |
Plans Available from | Municipal Agency |
Owner | View project details and contacts |
Architect | View project details and contacts |
Description | The project consists of renovation of the existing 17,426 SF one story campus building. Campus consists of three (3) separate buildings. Building A: 10,910 SF BUILDING B: 4,995 and BUILDING C: 1,080 SF. Construction of the buildings are wood framed, on continuous and spread footings and partially supported on concrete slab on grade. Work will include, BLDG A: Interior space renovations, new mechanical mezzanines, storage, seismic upgrades, complete demo, window replacement, reclad of exterior finishes including roofing, new domestic and fire water lines to support new fire protection system. New Mechanical System complete with DDC Controls, New Plumbing infrastructure, new lighting throughout and electrical work to support upgrades. BLDG B: Exterior Paint, New Roofing, New Mechanical Equipment utilizing existing ductwork and new lighting throughout. BLDG C – No work. BLDG A will be partially occupied in the Spring of 2022 and Fall of 2022, BLDG B will be occupied for the duration of the project. The project site is located at 3149 Oak Street in Florence, OR. |
||
Details |
|
||
Bidder's List | View project details and contacts | ||
Prospective Bidders | View project details and contacts | ||
Project Documents |
Engineered Spec Sheet Architectural Plans Other Documents |